Project 24AG0190
DPWH infrastructure contract
Contract ID:
24AG0190
Fingerprint:
019931be4cb480…0e2b99de36 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 20, 2025 (1 yr 5 mo ago) · Target/actual end Jan 20, 2026
Description:
CONSTRUCTION OF FMR, BARANGAY BARLO, MABINI, PANGASINAN
Category:
Trust Funds 2024
Implementing office:
DPWH Pangasinan 1st DEO · Region I
Contractor:
GED CONSTRUCTION · DPWH contractor code 13614
Contract amount:
₱9,601,721.05 (₱9.6M)
Funding source:
Outside Infra - Trust Funds 2024
Budget year:
2024
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25AG0148 | May 30, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION/CONSTRUCTION OF ROADS, MUNICIPALITY OF MABINI, PANGASINAN | On-Going | ₱19.4M |
| 25AG0166 | May 30, 2025 | SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG BURGOS-AGNO RD - K0303 + (-941) - K0309 + 559, BURGOS, PANGASINAN | On-Going | ₱69.8M |
| 25AG0102 | Apr 7, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, MABINI, PANGASINAN | On-Going | ₱9.6M |
| 25AG0005 | Mar 17, 2025 | ASSET PRESERVATION - CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - PANGASINAN - ZAMBALES RD - K0312 + 000 - K0312 + 770 | Completed | ₱19.2M |
| 25AG0054 | Feb 21, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BARANGAY MAAWI, ALAMINOS CITY, PANGASINAN | Completed | ₱4.9M |
| 25AG0107 | Feb 18, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CABINUANGAN, MABINI, PANGASINAN | Completed | ₱4.9M |
| 25AG0120 | Feb 18, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE 2, BARANGAY CABANAETAN, MABINI, PANGASINAN | Completed | ₱4.9M |
| 25AG0017 | Feb 12, 2025 | FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF BANK SLOPE ALONG BALINGCAGUING RIVER (CALZADA SECTION) STA. 024+918.8-STA. 025+309.4, BARANGAY CALZADA,MABINI, PANGASINAN | Completed | ₱70.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.