Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 24BA0029

DPWH infrastructure contract
Contract ID:
24BA0029
Fingerprint:
4788d43faba42b…49a017051f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 26, 2024 (2 yrs 7 mo ago) · Target/actual end Dec 15, 2025
Description:
CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BIP-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES -CONSTRUCTION OF RETAINING WALL AT RADIWAN PORT, BARANGAY RADIWAN, IVANA, BATANES
Category:
GAA 2024 SSP
Implementing office:
DPWH Batanes DEO · Region II
Contractor:
DEKM CONSTRUCTION · DPWH contractor code 32409
Contract amount:
₱7,829,791.64 (₱7.8M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
9ba0020fd157…Mar 5, 2024DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BATANES DEO₱7,829,791.64

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26BA0005Aug 5, 2026ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM:ASSET PRESERVATION PROGRAM: REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS,SLOPE COLLAPSE,AND LANDSLIDE-TERTIARY ROADS:BASCO-MAHATAO-IVANA-UYUGAN-IMNAJBU RD-K0009+000-K0009 + 051On-Going₱27.0M
25BA0058Aug 27, 2025CSSP: BIP- MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES: CONSTRUCTION OF MULTI-PURPOSE BUILDING (IVANA NATIONAL HIGH SCHOOL COVERED COURT), PHASE II, BRGY. RADIWAN, IVANA, BATANESOn-Going₱4.9M
25BA0069Aug 27, 2025CSSP: CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTORS- RAIN WATER COLLECTORS: CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS)Completed₱2.6M
25BA0005Aug 18, 2025OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION- REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS: BASCO- MAHATAO- IVANA- UYUGAN- IMNAJBU ROAD- K0011+760-K0011+791Completed₱48.5M
25BA0018Jun 18, 2025OO2:PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS: FLOOD MANAGEMENT PROGRAM:CONST./MAINT.OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS:CONST.OF SHORE PROTECTION STRUCTURE ALONG BASCO-MAHATAO-IVANA-UYUGAN-IMNAJBU ROAD,KADPIDAN SECTION,IVANA,BATANESOn-Going₱17.9M
25BA0030Jun 18, 2025BIP- PUBLIC WATER SUPPLY SYSTEM (LEVEL II OR III), CONSTRUCTION OF WATER SUPPLY SYSTEM (LEVEL I), BARANGAY RADIWAN, IVANA, BATANESOn-Going₱5.8M
25BA0062Jun 18, 2025CSSP: BIP- MULTIPURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES: CONSTRUCTION OF MULTI-PURPOSE BUILDING(IVANA ELEMENTARY SCHOOL COVERED COURT),PHASE I, BRGY. RADIWAN, IVANA, BATANESCompleted₱8.2M
25BA0012Mar 17, 2025CSSP: BIP- MULTIPURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES: CONSTRUCTION OF MULTIPURPOSE BUILDING, BRGY. RADIWAN, IVANA, BATANESOn-Going₱9.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.