Project 24BF0030
DPWH infrastructure contract
Contract ID:
24BF0030
Fingerprint:
767ff92ab9db8c…66cb6bc66b Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 18, 2024 (2 yrs 7 mo ago) · Target/actual end Jun 15, 2024
Description:
CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (DAY CARE CENTER), BARANGAY SANTOS, QUEZON, ISABELA
Category:
Buildings and Facilities
Implementing office:
DPWH Isabela 2nd DEO · Region II
Contractor:
JWU CONSTRUCTION AND SUPPLY · DPWH contractor code 48659
Contract amount:
₱2,962,716.50 (₱3.0M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 349bd4d5874f… | Feb 26, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ISABELA 2ND DEO | ₱2,962,727.48 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26BF0037 | Aug 3, 2026 | ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - LAGUINDAY PARALLEL BR. ALONG SANTIAGO-TUGUEGARAO RD, RIZAL KALINGA | On-Going | ₱56.1M |
| 25BF0104 | Oct 13, 2025 | RAINWATER COLLECTOR SYSTEM 1. VICTORIA ELEMENTARY SCHOOL, AURORA, ISABELA 2. BURGOS NATIONAL HIGH SCHOOL, BURGOS, ISABELA 3. HARANA ELEMENTARY SCHOOL, LUNA, ISABELA 4. BIMONTON INTEGRATED SCHOOL, MALLIG, ISABELA 5. MANANO ELEMENTARY SCHOOL MAIN, MALLIG, | On-Going | ₱2.5M |
| 25BF0068 | Aug 6, 2025 | OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, UPPER CHICO RIVER IRRIGATION SYSTEM, QUEZON, ISABELA | Completed | ₱14.0M |
| 25BF0089 | Aug 4, 2025 | CONSTRUCTION OF SCHOOL BUILDING, MINAGBAG INTEGRATED SCHOOL, QUEZON, ISABELA | Completed | ₱4.8M |
| 25BF0076 | Jul 9, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SAN JUAN, QUEZON, ISABELA | Completed | ₱5.8M |
| 25BF0078 | Jul 9, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (LEGISLATIVE BUILDING), BRGY. SAMONTE, QUEZON, ISABELA | Completed | ₱9.6M |
| 25BF0049 | Jun 30, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING, BARANGAY TUROD, QUEZON, ISABELA | On-Going | ₱4.8M |
| 25BF0029 | Jun 16, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (LEGISLATIVE BUILDING), BARANGAY SAMONTE, QUEZON, ISABELA | On-Going | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.