Project 24BH0299
DPWH infrastructure contract
Contract ID:
24BH0299
Fingerprint:
84f8969dea2f81…f42495d6c3 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 24, 2024 (2 yrs 1 mo ago) · Target/actual end Feb 15, 2025
Description:
SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF DEDEKKEL FLOOD CONTROL STRUCTURE, SECTION 1, DINAPIGUE ISABELA
Category:
Flood Control and Drainage
Implementing office:
DPWH Isabela 4th DEO · Region II
Contractor:
DALCON CONSTRUCTION · DPWH contractor code 40601
Contract amount:
₱96,500,000.00 (₱96.5M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 9e86b76e4770… | Sep 18, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ISABELA 4TH DEO | ₱95,533,323.59 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25BH0120 | Aug 18, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY DIBULO, DINAPIGUE, ISABELA | On-Going | ₱4.9M |
| 25BH0235 | Aug 18, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BUCAL SUR, DINAPIGUE, ISABELA | On-Going | ₱4.8M |
| 25BH0300 | Aug 11, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDING/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY AYOD, DINAPIGUE, ISABELA | On-Going | ₱2.9M |
| 25BH0147 | Aug 6, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BUCAL NORTE, DINAPIGUE, ISABELA | On-Going | ₱4.8M |
| 24BH0296 | Oct 7, 2024 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF DIMALUADE FLOOD CONTROL STRUCTURE, SECTION 1, DINAPIGUE, ISABELA | Completed | ₱96.3M |
| 24BH0297 | Oct 4, 2024 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BUCAL NORTE FLOOD CONTROL STRUCTURE, SECTION 3, DINAPIGUE, ISABELA | On-Going | ₱96.3M |
| 24BH0298 | Sep 24, 2024 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BUCAL NORTE FLOOD CONTROL STRUCTURE, SECTION 4, DINAPIGUE, ISABELA | Completed | ₱96.5M |
| 24BH0308 | Sep 6, 2024 | BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDING/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF BRGY. BUCAL NORTE MULTI-PURPOSE BUILDING, BRGY. BUCAL NORTE, DINAPIGUE, ISABELA | On-Going | ₱1.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.