Project 24CC0344

DPWH infrastructure contract
Contract ID:
24CC0344
Fingerprint:
00a2153806d715…2d70e0b7a5 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 18, 2024 (2 yrs 6 mo ago) · Target/actual end Aug 20, 2024
Description:
CONSTRUCTION OF RIVER PROTECTION STRUCTURE AND REHABILITATION OF WATERWAY ALONG ANGAT RIVER, K000+551 TO K000+701, BARANGAY BONGA MENOR, BUSTOS, BULACAN
Category:
GAA 2024 OO-2
Implementing office:
DPWH Bulacan 1st DEO · Region III
Contractor:
Contract amount:
₱48,999,739.43 (₱49.0M)
Funding source:
Regular Infra - GAA 2024 OO-2
Budget year:
2024

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CC0469May 23, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY MALAWAK, BUSTOS, BULACANOn-Going₱18.3M
25CC0470May 23, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE FACILITY (SPORTS COMPLEX), POBLACION, BUSTOS, BULACANOn-Going₱29.0M
25CC0492May 23, 2025CONSTRUCTION OF ROAD AT BARANGAY TALAMPAS , BUSTOS, BULACANOn-Going₱47.6M
25CC0534May 23, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TANAWAN, BUSTOS, BULACANOn-Going₱19.3M
25CD0219Apr 15, 2025IMPROVEMENT OF NORZAGARAY-ANGAT-BUSTOS DIVERSION ROAD IN NORZAGARAY AND ANGAT, BULACANOn-Going₱4.8M
25CC0210Apr 8, 2025CONSTRUCTION OF ROAD AT BARANGAY LICIADA, BUSTOS, BULACANOn-Going₱9.4M
25CC0393Apr 8, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BUSTOS, BULACANOn-Going₱14.5M
25CC0504Apr 4, 2025REHABILITATION OF BRIDGE, PUROK 7, BARANGAY BONGA MAYOR, BUSTOS, BULACANOn-Going₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.