Project 24CC0410
DPWH infrastructure contract
Contract ID:
24CC0410
Fingerprint:
c4e272bece506d…22a1d8943b Verified
Status:
On-Going
Physical progress:
100%
Timeline:
Start Apr 25, 2024 (2 yrs 6 mo ago)
Description:
CONSTRUCTION OF ROAD, PHASE 1, BARANGAY TARCAN, BALIUAG, BULACAN
Category:
Roads
Implementing office:
DPWH Bulacan 1st DEO · Region III
Contractor:
TBB CONSTRUCTION CORP. · DPWH contractor code 37026
Contract amount:
₱9,899,122.43 (₱9.9M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 3146d66481ea… | Apr 19, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BULACAN 1ST DEO | ₱9,702,006.63 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 24CL0214 | Feb 24, 2025 | CONSTRUCTION OF ROAD AT BARANGAY PUNDAQUIT, SAN ANTONIO, ZAMBALES | On-Going | ₱14.3M |
| 24CL0098 | May 23, 2024 | CONSTRUCTION/ RENOVATION OF MULTI-PURPOSE BUILDING, BRGY. RIZAL, SAN ANTONIO, ZAMBALES | Completed | ₱19.5M |
| 24CL0118 | May 21, 2024 | INSTALLATION/APPLICATION OF SIGNAGE AND PAVEMENT MARKINGS ALONG SAN MARCELINO - SAN ANTONIO - SAN NARCISO ROAD - K0162+400 - K0163+382, ANTIPOLO, POBLACION, SAN ANTONIO, ZAMBALES | Completed | ₱712.8K |
| 24CL0192 | May 7, 2024 | CONSTRUCTION OF ROAD, BARANGAY BURGOS, SAN ANTONIO, ZAMBALES | Completed | ₱14.5M |
| 24CL0108 | Mar 1, 2024 | CONSTRUCTION OF MULTI-PURPOSE BLDG. DIRITA ES, BRGY. EAST DIRITA, SAN ANTONIO, ZAMBALES | Completed | ₱15.6M |
| 24CL0047 | Feb 28, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE 2), BARANGAY SAN GREGORIO, SAN ANTONIO, ZAMBALES | Completed | ₱10.9M |
| 24CL0053 | Feb 22, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE 2), BARANGAY SAN NICOLAS, SAN ANTONIO, ZAMBALES | Completed | ₱5.9M |
| 24CL0094 | Feb 22, 2024 | CONCRETING OF ROAD SITIO NAMAAN, BRGY. LUNA, SAN ANTONIO, ZAMBALES | Completed | ₱14.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.