Physical progress:
100%
Timeline:
Start Apr 22, 2024 (2 yrs 6 mo ago) · Target/actual end Jul 16, 2024
Description:
ASSET PRESERVATION PROGRAM: REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - CANDABA - SN MIGUEL RD - K0073+290 - K0073+411, K0078+785 - K0079+116, K0079+443 - K0079+558, K0079+574 - K0079+828, K0081+700 - K0081+775, CAN
Category:
Roads
Implementing office:
DPWH Pampanga 1st DEO · Region III
Contractor:
SOLID PILE CONSTRUCTION · DPWH contractor code 50399
Contract amount:
₱21,809,779.47 (₱21.8M)
Funding source:
Regular Infra - GAA 2024 OO-1
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 962649e5a84e… | Apr 15, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PAMPANGA 1ST DEO | ₱21,809,779.47 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CG0293 | Oct 7, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, SAN LUIS, PAMPANGA | Completed | ₱14.1M |
| 25CG0264 | Aug 28, 2025 | CONCRETING OF FARM-TO-MARKET ROAD AT BRGY. TALANG, CANDABA, PAMPANGA | Completed | ₱18.9M |
| 25CG0252 | Aug 19, 2025 | CONCRETING OF FARM-TO-MARKET-ROAD AT BRGY. LOURDES, CANDABA, PAMPANGA | On-Going | ₱18.9M |
| 25CG0036 | Jul 29, 2025 | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - BALIWAG - CANDABA - STA ANA RD - K0058+(-555) - K0058+000, K0062+000 - K0062+870, K0063+888 - K0063+984, K0071+069 - K0071+828 | Terminated | ₱0 |
| 25C00520 | Jul 27, 2025 | CONVERGENCE & SPL. SUPPORT PROG.-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)-REHAB. OF ROAD, CANDABA-BALIWAG ROAD (PASIG-POBLACION SECT.) CANDABA, P | On-Going | ₱236.4M |
| 25CG0141 | May 30, 2025 | CONCRETING OF BRGY. SAN JUAN FARM-TO-MARKET ROAD, BRGY. SAN JUAN, SAN LUIS, PAMPANGA | Completed | ₱4.7M |
| 25CG0113 | Apr 2, 2025 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REPAIR / REHABILITATION OF CONCRETE SLOPE PROTECTION ALONG PAMPANGA RIVER, BRGY. SA | Terminated | ₱0 |
| 25CG0034 | Feb 28, 2025 | FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SLOPE PROTECTION STRUCTURE OF VICTORIA DRAINAGE SYSTEM AT ANGAT-MAASIM RIS, CANDABA, PAMPANGA | Completed | ₱14.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.