Project 24CG0299

DPWH infrastructure contract
Contract ID:
24CG0299
Fingerprint:
c2c802c0b5bbf2…f4441bd203 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 12, 2024 (2 yrs 2 mo ago) · Target/actual end Mar 24, 2025
Description:
CONCRETING OF MAPANIQUI FMR, CANDABA, PAMPANGA
Category:
Roads
Implementing office:
DPWH Pampanga 1st DEO · Region III
Contractor:
Contract amount:
₱18,865,542.74 (₱18.9M)
Funding source:
Outside Infra - Trust Funds 2024
Budget year:
2024

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CG0293Oct 7, 2025BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, SAN LUIS, PAMPANGACompleted₱14.1M
25CG0264Aug 28, 2025CONCRETING OF FARM-TO-MARKET ROAD AT BRGY. TALANG, CANDABA, PAMPANGACompleted₱18.9M
25CG0252Aug 19, 2025CONCRETING OF FARM-TO-MARKET-ROAD AT BRGY. LOURDES, CANDABA, PAMPANGAOn-Going₱18.9M
25CG0036Jul 29, 2025ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - BALIWAG - CANDABA - STA ANA RD - K0058+(-555) - K0058+000, K0062+000 - K0062+870, K0063+888 - K0063+984, K0071+069 - K0071+828Terminated₱0
25C00520Jul 27, 2025CONVERGENCE & SPL. SUPPORT PROG.-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)-REHAB. OF ROAD, CANDABA-BALIWAG ROAD (PASIG-POBLACION SECT.) CANDABA, POn-Going₱236.4M
25CG0141May 30, 2025CONCRETING OF BRGY. SAN JUAN FARM-TO-MARKET ROAD, BRGY. SAN JUAN, SAN LUIS, PAMPANGACompleted₱4.7M
25CG0113Apr 2, 2025SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REPAIR / REHABILITATION OF CONCRETE SLOPE PROTECTION ALONG PAMPANGA RIVER, BRGY. SATerminated₱0
25CG0034Feb 28, 2025FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SLOPE PROTECTION STRUCTURE OF VICTORIA DRAINAGE SYSTEM AT ANGAT-MAASIM RIS, CANDABA, PAMPANGACompleted₱14.0M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.