Project 24CJ0191

DPWH infrastructure contract
Contract ID:
24CJ0191
Fingerprint:
ba937910b17402…ab4a428642 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 12, 2024 (2 yrs 8 mo ago) · Target/actual end Mar 18, 2024
Description:
CONSTUCTION OF ROAD, BRGY. TOLEGA SUR TO BRGY. BURGOS, MONCADA, TARLAC
Category:
Roads
Implementing office:
DPWH Tarlac DEO · Region III
Contractor:
SPYS BUILDERS CORP. (FORMERLY: SPYS BUILDERS) · DPWH contractor code 41756
Contract amount:
₱9,652,027.70 (₱9.7M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CJ0192Jun 20, 2025REHABILITATION OF CAMPOSANTO 1 - NORTE - TUBECTUBANG ROAD (SEGMENT 3), MONCADA, TARLACCompleted₱96.5M
25CJ0238Jun 20, 2025CONSTRUCTION OF MONCADA - PANIQUI DIVERSION ROAD (SEGMENT 5), MONCADA, TARLACOn-Going₱96.5M
25CJ0081May 22, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY CAPAOAYAN, MONCADA, TARLACCompleted₱4.9M
25CJ0210May 22, 2025INSTALLATION OF ROAD SAFETY DEVICES AND SOLAR LED STREET LIGHTS ALONG CAMPOSANTO 1 - NORTE - TUBECTUBANG ROAD TO MANILA NORTH RD (ANNEX 2), MONCADO, TARLACCompleted₱47.3M
25CJ0212May 22, 2025INSTALLATION OF ROAD SAFETY DEVICES AND SOLAR LED STREET LIGHTS ALONG MONCADA-PANIQUI DIVERSION RD TO MANILA NORTH RD (ANNEX 2), TARLACCompleted₱47.4M
25CJ0163May 16, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BAKET-BAKET RIVER (ANNEX 8), MONCADA, TARLACOn-Going₱96.5M
25CJ0226May 16, 2025IMPROVEMENT OF MONCADA ROAD NETWORK (ANNEX 2), MONCADA, TARLACCompleted₱29.7M
25CJ0161Apr 8, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG BAKET - BAKET RIVER, MONCADA, TARLAC (SEGMENT 14)Completed₱74.3M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.