Project 24CN0076
DPWH infrastructure contract
Contract ID:
24CN0076
Fingerprint:
0aa87197c6ecee…249d9589d9 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 7, 2024 (2 yrs 6 mo ago) · Target/actual end Dec 18, 2024
Description:
CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BRGY. LUAL, CASIGURAN, AURORA
Category:
GAA 2024 SSP
Implementing office:
DPWH Aurora DEO · Region III
Contractor:
GERRA CONSTRUCTION INCORPORATED · DPWH contractor code 29359
As listed: GERRA CONSTRUCTION INCORPORATED (FORMERLY: GERRA CONSTRUCTION)
Contract amount:
₱48,250,000.00 (₱48.3M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| b784a33fe2dc… | Apr 29, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AURORA DEO | ₱47,285,493.45 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CN0028 | May 28, 2025 | REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, DIOS BR. (B03279LZ) ALONG BALER - CASIGURAN RD (DINADIAWAN - CASIGURAN SECT) | On-Going | ₱4.9M |
| 25CN0030 | May 28, 2025 | REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, PUGO BR. (B03278LZ) ALONG BALER - CASIGURAN RD (DINADIAWAN - CASIGURAN SECT) | On-Going | ₱4.9M |
| 25CN0118 | May 26, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY 2, CASIGURAN, AURORA | Completed | ₱6.9M |
| 25CN0142 | May 26, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY ESTEVES, CASIGURAN, AURORA | Completed | ₱5.0M |
| 25CN0140 | May 23, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY DITINAGYAN, CASIGURAN, AURORA | Completed | ₱5.0M |
| 25CN0145 | May 23, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LUAL, CASIGURAN, AURORA | Completed | ₱5.0M |
| 25C00004 | Apr 8, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF CASALOGAN FLOOD CONTROL STRUCTURE, CASIGURAN, AURORA | On-Going | ₱141.9M |
| 25CN0078 | Apr 3, 2025 | CONSTRUCTION OF ROAD, BARANGAY DIBACONG, CASIGURAN, AURORA | On-Going | ₱9.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.