Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 24DD0300

DPWH infrastructure contract
Contract ID:
24DD0300
Fingerprint:
14bbc60a6ff4ac…2764d48b3b Verified
Status:
On-Going
Physical progress:
100.0%
Timeline:
Start Mar 27, 2025 (1 yr 7 mo ago)
Description:
CONCRETING OF BARANGAY PULANGBATO FMR, BARANGAY PULANGBATO, SAN JUAN, BATANGAS
Category:
Trust Funds 2024
Implementing office:
DPWH Batangas 4th DEO · Region IV-A
Contractor:
ALPHA VECTOR CONSTRUCTION AND SUPPLY · DPWH contractor code 44630
Contract amount:
₱19,303,115.00 (₱19.3M)
Funding source:
Outside Infra - Trust Funds 2024
Budget year:
2024

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25D00017May 21, 2025CONSTRUCTION OF BY-PASS AND DIVERSION ROADSSAN JUAN BYPASS (ROSARIO-SAN JUAN-LAIYA TOURISM BYPASS ROAD) CANDELARIA-SAN JUAN-ROSARIO, PACKAGE 4, SAN JUAN BATANGASOn-Going₱89.4M
25D00018Apr 10, 2025CONSTRUCTION OF REVETMENT ALONG MALAKING ILOG RIVER, PHASE 1, BARANGAY MARAYKIT, SAN JUAN, BATANGASOn-Going₱94.1M
25D00027Apr 10, 2025WIDENING OF PERMANENT BRIDGES BANTILAN BR. (B02946LZ) ALONG SN JUAN-CANDELARIA JCT-CANDELARIA-BOLBOC RDOn-Going₱34.7M
25D00128Apr 10, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MALAKING TUBIG RIVER, PHASE 3, TIAONG, QUEZONOn-Going₱95.1M
25D00016Apr 4, 2025CONSTRUCTION OF BY-PASS AND DIVERSION ROADS SAN JUAN BYPASS (ROSARIO-SAN JUAN-LAIYA TOURISM BYPASS ROAD) CANDELARIA-SAN JUAN-ROSARIO, PACKAGE 3, SAN JUAN BATANGASOn-Going₱230.5M
25D00054Apr 4, 2025CONSTRUCTION OF BY-PASS AND DIVERSION ROADS SAN JUAN BYPASS (ROSARIO-SAN JUAN-LAIYA TOURISM BYPASS ROAD), BATANGASOn-Going₱47.0M
24DD0303Mar 27, 2025CONCRETING OF BARANGAY SAMPIRO FMR, BARANGAY SAMPIRO, SAN JUAN, BATANGASOn-Going₱14.5M
24DD0304Mar 27, 2025CONCRETING OF BARANGAY LAIYA IBABAO FMR, BARANGAY LAIYA IBABAO, SAN JUAN, BATANGASOn-Going₱14.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.