Project 24DG0059

DPWH infrastructure contract
Contract ID:
24DG0059
Fingerprint:
40d1abbbb90c6c…cccdbbbad2 Verified
Status:
Terminated
Physical progress:
0%
Timeline:
Start Mar 21, 2024 (2 yrs 7 mo ago) · Target/actual end Jul 4, 2025
Description:
CONST OF FLOOD MITIGATION STRUCT-CONST OF KAY-AKLE RIS WATER MGMT FC PROJ OF KAY-AKLE RIVER,MARAGON
Category:
GAA 2024 OO-2
Implementing office:
DPWH Cavite 2nd DEO · Region IV-A
Contractor:
ZLMA CONSTRUCTION · DPWH contractor code 53608
Contract amount:
₱0.00 (₱0)
Funding source:
Regular Infra - GAA 2024 OO-2
Budget year:
2024

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
92db41e1705b…Feb 27, 2024DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAVITE II DISTRICT₱9,486,308.19

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25DG0053Jun 18, 2025CONST. OF MULTI-PURPOSE BLDG. (GYMNASIUM) AT BRGY. CASTAÑOS, GEN. E. AGUINALDO, CAVITEOn-Going₱48.8M
25D00121Apr 7, 2025CONSTRUCTION OF MISSING LINKS/ NEW ROADS GENERAL AGUINALDO-MAGALLANES-NASUGBU ROAD (EAST-WEST ROAD), MAGALLANES-GEN. AGUINALDO SECTION, PACKAGE 6, CAVITEOn-Going₱112.9M
25DG0044Mar 25, 2025CONST. OF WATER SUPPLY SYSTEM, BRGY. CASTAÑOS LEJOS, GEN. E. AGUINALDO, CAVITEOn-Going₱4.9M
24DG0098Sep 23, 2024BIP CONST. OF MULTI-PURPOSE BUILDING (HOSPITAL BLDG.), GEN. E. AGUINALDO, CAVITEOn-Going₱49.0M
24DG0087Jul 12, 2024BIP-CONST OF ROAD, SITIO BOLBOK AMUNTAY, BRGY CASTAÑOS LEJOS, GEN E AGUINALDO,CAVITECompleted₱10.4M
24DG0080May 24, 2024BIP-MPB/FACILITIES TO SUPPORT SOCIAL SERVICES-CONST OF MPB IN BRGY POB I, GEN.E.AGUINALDO, CAVITECompleted₱9.8M
24DG0088Apr 10, 2024CONST OF ROAD,SITIO MATAAS NA LUPA, BRGY TABORA-BRGY LUMIPA, GEN AGUINALDO, CAVITECompleted₱4.8M
24D00049Mar 22, 2024CONSTRUCTION OF MISSING LINKS/ NEW ROADS GENERAL AGUINALDO - MAGALLANES - NASUGBU ROAD (EAST - WEST ROAD), MAGALLANES - GEN. AGUINALDO SECTION, PACKAGE 3, CAVITEOn-Going₱70.4M