Project 24DH0046
DPWH infrastructure contract
Contract ID:
24DH0046
Fingerprint:
cf9d53dc62a4f5…d2f6a93b6c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 7, 2024 (2 yrs 6 mo ago) · Target/actual end Dec 2, 2024
Description:
CONSTRUCTION OF MULTI PURPOSE BUILDING, BRGY. SAN BUENAVENTURA, LUISIANA, LAGUNA
Category:
GAA 2024 SSP
Implementing office:
DPWH Laguna 1st DEO · Region IV-A
Contractor:
E. AGLAHI URBAN BUILDERS · DPWH contractor code 44113
Contract amount:
₱4,800,634.33 (₱4.8M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DH0006 | May 15, 2025 | PREVENTIVE MAINTENANCE-SECONDARY ROADS- PAGSANJAN-LUCBAN RD K0107+220-K0107+865, LUISIANA, LAGUNA | Completed | ₱38.4M |
| 25DH0050 | May 15, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SANTO TOMAS, LUISIANA, LAGUNA | Completed | ₱4.8M |
| 24DH0043 | Apr 14, 2024 | PREVENTIVE MAINTENANCE-SECONDARY ROADS-PAGSANJAN-LUCBAN RD-K0112+292 TO K0113+804, LUISIANA, LAGUNA | Completed | ₱96.4M |
| 24D00021 | Feb 28, 2024 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADSLUISIANA - MAUBAN DIVERSION ROAD, LUISIANA SECTION, LAGUNA | On-Going | ₱84.4M |
| 24DH0017 | Feb 20, 2024 | ROAD WIDENING-SECONDARY ROADS PAGSANJAN-LUCBAN RD. K0104+434-K0104+740, LUISIANA, LAGUNA | Completed | ₱19.6M |
| 23D00090 | Sep 4, 2023 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS LUISIANA - MAUBAN DIVERSION ROAD, LUISIANA SECTION, LAGUNA | On-Going | ₱57.9M |
| 23DH0077 | Jul 29, 2023 | OPENING AND CONCRETING OF BRGY. SAN ANTONIO FMR, BRGY. SAN ANTONIO, LUISIANA, LAGUNA | Completed | ₱9.9M |
| 23DH0078 | Jul 29, 2023 | CONCRETING OF BRGY. SAN JOSE FMR, BRGY. SAN JOSE, LUISIANA, LAGUNA | Completed | ₱11.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.