Project 24DJ0054
DPWH infrastructure contract
Contract ID:
24DJ0054
Fingerprint:
24c9d1969e6ce2…abf0c91747 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 13, 2024 (2 yrs 8 mo ago) · Target/actual end Sep 9, 2024
Description:
CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP)- SPECIAL ROAD FUND-MOTOR VEHICLE USE'S CHARGE (MVUC) AS PER R.A. 11239, IMPROVEMENT OF INTERSECTION-CANDELARIA BY-PASS ROAD (S06103LZ) - K0107+714 AND PAHINGA-KINATIHAN ROAD
Category:
Roads
Implementing office:
DPWH Quezon 2nd DEO · Region IV-A
Contractor:
GROUNDED ERL BUILDERS INCORPORATED · DPWH contractor code 52304
Contract amount:
₱9,800,000.00 (₱9.8M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 480e3287795e… | Jan 31, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - QUEZON 2ND ED | ₱9,564,800.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DJ0146 | Aug 29, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING PHASE 3, BARANGAY PAHINGA NORTE, CANDELARIA, QUEZON | On-Going | ₱48.0M |
| 25DJ0024 | Jun 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY BUKAL NORTE, CANDELARIA, QUEZON | Completed | ₱4.8M |
| 25DJ0025 | Jun 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY MANGILAG SUR, CANDELARIA, QUEZON | On-Going | ₱4.9M |
| 25DJ0026 | Jun 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY MASALUKOT 2, CANDELARIA, QUEZON | Completed | ₱5.8M |
| 25DJ0054 | Jun 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY MAYABOBO, CANDELARIA, QUEZON | Completed | ₱4.8M |
| 25DJ0074 | Jun 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY PAHINGA NORTE, CANDELARIA, QUEZON | On-Going | ₱4.8M |
| 25DJ0109 | Jun 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY POBLACION, CANDELARIA, QUEZON | On-Going | ₱9.6M |
| 25DJ0113 | Jun 5, 2025 | OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS, CANDELARIA BYPASS RD - K0106+935 - K0107+124.5 | On-Going | ₱18.1M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.