Project 24ED0057
DPWH infrastructure contract
Contract ID:
24ED0057
Fingerprint:
fe171fc0b27d03…77b5bad560 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 8, 2024 (2 yrs 9 mo ago) · Target/actual end Aug 27, 2024
Description:
CONSTRUCTION OF SAN TEODORO MULTI - PURPOSE BUILDING, SAN TEODORO, ORIENTAL MINDORO
Category:
GAA 2024 SSP
Implementing office:
DPWH Mindoro Oriental DEO · MIMAROPA Region
Contractor:
2332 BUILDERS · DPWH contractor code 44813
Contract amount:
₱9,899,868.72 (₱9.9M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| bce4153a567d… | Jan 30, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - MINDORO ORIENTAL D | ₱9,599,180.40 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25ED0004 | Feb 18, 2025 | CONSTRUCTION OF DRAINAGE, SITIO CROSSING, BRGY. CALSAPA, SAN TEODORO, ORIENTAL MINDORO | Completed | ₱4.9M |
| 25ED0025 | Feb 18, 2025 | REHABILITATION OF BRIDGE, BARANGAY TACLIGAN, SAN TEODORO, ORIENTAL MINDORO | Completed | ₱29.7M |
| 25ED0056 | Feb 18, 2025 | CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY LUMANGBAYAN, SAN TEODORO, ORIENTAL MINDORO | Completed | ₱1.9M |
| 25ED0023 | Feb 12, 2025 | CONSTRUCTION OF ROAD, CAAGUTAYAN - BIGAAN CIRCUMFERENTIAL ROAD, SAN TEODORO, ORIENTAL MINDORO | Completed | ₱29.4M |
| 24ED0140 | Apr 1, 2024 | COMPLETION OF MULTI - PURPOSE BUILDING (COVERED COURT), CAAGUTAYAN, SAN TEODORO, ORIENTAL MINDORO | Completed | ₱2.0M |
| 24ED0099 | Feb 22, 2024 | IMPROVEMENT OF ROAD, SITIO MASASA - SITIO DELINQUENTE, BARANGAY TACLIGAN, SAN TEODORO, ORIENTAL MINDORO | Completed | ₱19.8M |
| 23ED0102 | May 31, 2023 | CONSTRUCTION OF SOLAR WATER SYSTEM, MUNICIPALITY OF SAN TEODORO, ORIENTAL MINDORO | Completed | ₱9.8M |
| 23E00169 | Apr 13, 2023 | BASIC INFRASTRUCTURE PROGRAM- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF SUBAAN FLOOD CONTROL SYSTEM, BRGY. CALSAPA-BRGY. BIGAAN SECTION (UPSTREAM/RS), ORIENTAL MINDORO | Completed | ₱99.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.