Project 24EH0165
DPWH infrastructure contract
Contract ID:
24EH0165
Fingerprint:
6de62a4fb156ab…d47d48ae42 Verified
Status:
On-Going
Physical progress:
74.1%
Timeline:
Start Dec 6, 2024 (1 yr 11 mo ago)
Description:
CONSTRUCTION OF 3STY15CL, LOOC NATIONAL HIGH SCHOOL, LOOC, ROMBLON
Category:
GAA 2024 DepEd BEFF
Implementing office:
DPWH Romblon DEO · MIMAROPA Region
Contractor:
ROLCO CONSTRUCTION & DEVELOPMENT CORPORATION ( FOR · DPWH contractor code 29686
Location:
Contract amount:
₱63,306,517.15 (₱63.3M)
Funding source:
Outside Infra - GAA 2024 DepEd BEFF
Budget year:
2024
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26EH0032 | Aug 11, 2026 | REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - LOOC (COGON TULAY) - ODIONGAN RD - K0103+198-K0103+330.70, K0103+338.56 - K0103+362.50, TABLAS ISLAND, ROMBLON | On-Going | ₱4.4M |
| 25EH0084 | Jul 28, 2025 | ROAD WIDENING ALONG TABLAS CIRCUMFERENTIAL ROAD, K0098+820.00-K0099+202.90, K0099+231.13 - K0100+350.23 (AS PER ACTUAL), K0098+820.00-K0099+199.90, K0099+231.13 - K0100+341.23 (AS PER RBIA), TABLAS ISLAND, ROMBLON | On-Going | ₱96.2M |
| 25EH0129 | Jul 10, 2025 | CONSTRUCTION OF LIMON NORTE WATER IMPOUNDING PROJECT, LOOC, ROMBLON | On-Going | ₱48.0M |
| 25EH0155 | May 27, 2025 | CONSTRUCTION OF ROAD, PHASE 2, BARANGAY BAGSIK - SITIO LOBTON TO BARANGAY MADALAG (ALCANTARA) LEADING TO BARANGAY TUGUIS, LOOC, ROMBLON | On-Going | ₱93.6M |
| 25EH0158 | May 27, 2025 | CONSTRUCTION OF BRGY. PILI TO BRGY. LIMON SUR ROAD (PHASE 2), LOOC, ROMBLON | On-Going | ₱119.9M |
| 25EH0022 | May 26, 2025 | CONSTRUCTION OF CAUSEWAY ALONG PUNTA, LOOC, ROMBLON, TABLAS ISLAND, ROMBLON | On-Going | ₱71.3M |
| 25EH0109 | May 26, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING (GOVERNMENT CENTER) AT BARANGAY PUNTA, LOOC, ROMBLON | On-Going | ₱9.7M |
| 25EH0114 | May 26, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY TUGUIS, LOOC, ROMBLON | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.