Project 24EH0179
DPWH infrastructure contract
Contract ID:
24EH0179
Fingerprint:
cf820273079526…4df381043c Verified
Status:
On-Going
Physical progress:
99.6%
Timeline:
Start Mar 24, 2025 (1 yr 7 mo ago)
Description:
CONSTRUCTION OF LUMBANG WESTE FLOOD CONTROL STRUCTURE ALONG LUMBANG RIVER PHASE 2, CAJIDIOCAN, ROMBLON
Category:
Unprogrammed Appropriations 2024
Implementing office:
DPWH Romblon DEO · MIMAROPA Region
Contractor:
SUNWEST, INC. · DPWH contractor code 15906
As listed: SUNWEST, INC. (FORMERLY: SUNWEST CONSTRUCTION & DEVELOPMENT CORPORATION)
Contract amount:
₱130,376,539.70 (₱130.4M)
Funding source:
Outside Infra - Unprogrammed Appropriations 2024
Budget year:
2024
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25EH0031 | May 26, 2025 | CONSTRUCTION OF CAMBALO FLOOD CONTROL STRUCTURE, CAJIDIOCAN, ROMBLON | On-Going | ₱48.3M |
| 25EH0115 | May 23, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY DANAO, CAJIDIOCAN, ROMBLON | On-Going | ₱4.9M |
| 25EH0135 | May 22, 2025 | CONCRETING OF SITIO ALAHAG, BRGY. DANAO, FMR, BRGY. DANAO, CAJIDIOCAN, ROMBLON | On-Going | ₱39.1M |
| 25EH0039 | Apr 11, 2025 | CONSTRUCTION OF TAGUILOS CIS, SLOPE PROTECTION WORKS (UPSTREAM AND DOWNSTREAM, LEFT AND RIGHT SIDE EMBANKMENT), CAJIDIOCAN, ROMBLON | Completed | ₱9.7M |
| 25E00263 | Apr 6, 2025 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES- CONST. OF COASTAL ROAD/SHORE PROTECTION ALONG BRGY. CAMBIJANG-BRGY. POBLACION, STA. 000+748.60-STA. 001+020, CAJIDIOCAMN, ROMBLON | On-Going | ₱230.9M |
| 25E00264 | Apr 6, 2025 | SUSTAINABLE INFRASTRUCTURE ALLEVIATING GAPS (SIPAG)- COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES- CONST. OF COASTAL ROAD/SHORE PROTECTION ALONG BRGY. CAMBIJANG, STA. 000+398.65-STA. 000+440; STA. 000+520-STA. 000+740, CAJIDIOCAN, SIBUYAN IS | On-Going | ₱230.9M |
| 25EH0028 | Mar 25, 2025 | ACCESS ROAD LEADING TO CAJIDIOCAN VIEWDECK, CAJIDIOCAN, ROMBLON | Completed | ₱9.6M |
| 25EH0033 | Mar 24, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CAMBAJAO BRIDGE DS, PHASE 2, CAJIDIOCAN, ROMBLON | On-Going | ₱142.6M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.