Project 24F00352
DPWH infrastructure contract
Contract ID:
24F00352
Fingerprint:
f44ddbf446ea80…38ad7b29b0 Verified
Status:
On-Going
Physical progress:
100%
Timeline:
Start Nov 29, 2024 (1 yr 11 mo ago)
Description:
CONSTRUCTION OF AN INFIRMARY - DR. EMILIO B. ESPINOSA, SR. MEMORIAL STATE COLLEGE OF AGRICULTURE AND TECHNOLOGY, MANDAON, MASBATE
Category:
GAA 2024 SUCs Infrastructure Projects
Implementing office:
DPWH Region V · Region V
Contractor:
3R3M CONSTRUCTION AND SUPPLY CORPORATION (FORMERLY: 3R3M CONSTRUCTION AND SUPPLY) · DPWH contractor code 45410
Contract amount:
₱14,402,429.27 (₱14.4M)
Funding source:
Outside Infra - GAA 2024 SUCs Infrastructure Projects
Budget year:
2024
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26FI0026 | Aug 4, 2026 | CSSP - SIPAG - ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES - CONSTRUCTION OF JCT NATIONAL ROAD - BARANGAY VILLA ALVAREZ - BARANGAY SALVACION, BALUD, MASBATE, STA. 2+100 - STA. 3+230 | On-Going | ₱46.4M |
| 26FI0031 | Aug 4, 2026 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT -CONSTRUCTION OF MISSING LINKS/ NEW ROADS - MANDAON - DAYHAGAN ROAD, MASBATE, STA. 7 +155 - STA. 7+380 | On-Going | ₱24.9M |
| 25FI0062 | Jan 9, 2026 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION / REHABILITATION OF WATER SUPPLY / SEPTAGE SEWERAGE / RAIN WATER COLLECTORS - WATER SUPPLY SYSTEM - CONSTRUCTION OF SOLAR WATER SYSTEM, MANDAON, MASBATE | On-Going | ₱17.3M |
| 25FI0005 | Apr 2, 2025 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - JCT. CROSSING - MANDAON RD (S00037MT) K0048+970 - K0049+077, MANDAON, MASBA | On-Going | ₱5.3M |
| 25FI0033 | Mar 21, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BARANGAY SAN PABLO AND BARANGAY CANOMOY, MAN | On-Going | ₱9.7M |
| 25FI0008 | Mar 4, 2025 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/ NEW ROADS - MANDAON - DAYHAGAN ROAD, MASBATE (PACKAGE 1), MANDAON, MASBATE | Completed | ₱28.8M |
| 25FI0025 | Mar 4, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES - CONSTRUCTION OF ROAD, BARANGAY BAT-ONGAN TO D | On-Going | ₱43.4M |
| 25FI0027 | Mar 4, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES - CONSTRUCTION OF ROAD, BARANGAY MAPITOGO TO BA | On-Going | ₱24.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.