Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 24FE0052

DPWH infrastructure contract
Contract ID:
24FE0052
Fingerprint:
a02d888b74da25…451ff1ca7e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 7, 2024 (2 yrs 5 mo ago) · Target/actual end Nov 13, 2024
Description:
CONCRETING OF SITIO GUILID, BRGY. TARIRIC FMR, BRGY. TARIRIC, MINALABAC, CAMARINES SUR
Category:
Roads
Implementing office:
Contractor:
PRIMARCH CONSTRUCTION OPC · DPWH contractor code 55799
Contract amount:
₱29,849,429.84 (₱29.8M)
Funding source:
Outside Infra - GAA 2024 DA FMR
Budget year:
2024

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
4f44d67a039f…Jun 6, 2024DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAMARINES SUR 2ND₱29,552,026.84

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25FE0032Jun 20, 2025CONSTRUCTION/REHABILITATION OF RAINWATER COLLECTORS SYSTEM (RWCS) IN PUBLIC FACILITIES 1) MALBONG ELEMENTARY SCHOOL, BRGY. MALBONG, GAINZA, CAMARINES SUR 2) CAGBUNGA ELEMENTARY SCHOOL, BRGY. CAGBUNGA, GAINZA, CAMARINES SUR 3) DAHILIG ELEMENTARY SCHOOL, BRCompleted₱2.6M
25F00222Jun 11, 2025ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CAMARINES SUR EXPRESSWAY PACKAGE 17, CAMARINES SUR, MINALABAC, CAMARINES SUR (2ND LEGISLATIVE DISTRICT)On-Going₱190.1M
25F00223Jun 5, 2025ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-CAMARINES SUR EXPRESSWAY PACKAGE 18, CAMARINES SUR, MINALABAC, CAMARINES SUR (2ND LEGISLATIVE DISTRICT)On-Going₱190.1M
24FE0070Mar 24, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BICOL RIVER (UPSTREAM, LEFTSIDE), BARANGAY BALIUAG VIEJO, MINALABAC, CAMARINES SURCompleted₱47.8M
25FE0014Mar 7, 2025OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BICOL RIVER (DOWNSTREAM), BARANGAY BALIUAG NUEVO, MINALABAC, CAMAOn-Going₱62.1M
24FN0092Feb 14, 2025OO2:PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONST./REHAB. OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS & PRINCIPAL RIVERS-CONST. OF FLOOD CONTROL STRUCT., BICOL RIVER REV'T WALL, BRGY. SAN RAMON SEC., BULA, CAMSUROn-Going₱144.8M
24FE0062Oct 7, 2024CSSP: BASIC INFRASTRUTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, SITIO GILID, BARANGAY TARIRIC, MINALABAC, CAMARINES SUR (REBIDDING)Completed₱2.0M
24FE0058Jun 19, 2024CONCRETING OF BRGY. TARIRIC, MINALABAC, CAMARINES SURCompleted₱9.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.