Project 24FI0033
DPWH infrastructure contract
Contract ID:
24FI0033
Fingerprint:
295f891b74a565…67a9aea405 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 28, 2024 (2 yrs 8 mo ago) · Target/actual end Dec 13, 2024
Description:
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A.11239 - INSTALLATION OF ROAD SAFETY DEVICES AND STREET LUMINAIRES ALONG MASBATE-CATAINGAN-PLACER RD (S00005MT) - K0004+000 - K0007+000, MOBO, MASBA
Category:
GAA 2024 SSP
Implementing office:
DPWH Masbate 2nd DEO · Region V
Contractor:
ACETAN ENTERPRISES · DPWH contractor code 51557
Contract amount:
₱29,399,922.76 (₱29.4M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 4a29610749a7… | Feb 15, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - MASBATE 2ND DEO | ₱28,811,924.32 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26FI0025 | Aug 4, 2026 | ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - MASBATE - CATAINGAN - PLACER RD - K0009+502 - K0010+289, MOBO, MASBATE | On-Going | ₱63.8M |
| 26FI0021 | Jun 26, 2026 | ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE - WIDENING OF PERMANENT BRIDGES - LIPATA BR. (B00083MT) ALONG MASBATE - CATAINGAN - PLACER RD., MOBO, MASBATE | On-Going | ₱6.7M |
| 25FI0065 | Jan 9, 2026 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION /REHABILITATION OF WATER SUPPLY / SEPTAGE AND SEWERAGE / RAIN WATER COLLECTORS - WATER SUPPLY SYSTEM - CONSTRUCTION OF SOLAR WATER SYSTEM, MOBO, MASBATE | On-Going | ₱17.3M |
| 25FI0045 | Jul 2, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDING/ FACILITIES TO SUPPORT SOCIAL SERVICE - CONSTRUCTION OF MULTI - PURPOSE BUILDING, (SEDIMENTATION FACILITY), BARANGAY PINAMALATICAN, MOBO, MASBATE | On-Going | ₱42.8M |
| 24FI0104 | May 28, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY JOLJOGON TO B | On-Going | ₱14.5M |
| 25FI0004 | Apr 2, 2025 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - MASBATE - CATAINGAN - PLACER RD (S00005MT) - K0009+101.5 - K0009+502, MOBO, MASBATE | On-Going | ₱29.6M |
| 25FI0021 | Mar 4, 2025 | ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BAÑADERO RIVER, MOBO, MAS | On-Going | ₱96.5M |
| 24FI0002 | Nov 25, 2024 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - MASBATE - CATAINGAN - PLACER RD. (S00005MT) K0009+076 - K0009+091 | On-Going | ₱2.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.