Project 24G00035
DPWH infrastructure contract
Contract ID:
24G00035
Fingerprint:
3b5c4facec3e24…fe246a1995 Verified
Status:
On-Going
Physical progress:
98.5%
Timeline:
Start Feb 14, 2024 (2 yrs 8 mo ago)
Description:
CONSTRUCTION OF REVETMENT WALL ALONG AKLAN RIVER, MADALAG, AKLAN (PACKAGE 1)
Category:
GAA 2024 OO-2
Implementing office:
DPWH Region VI · Region VI
Contractor:
MEGAGOLD CONSTRUCTION AND DEVELOPMENT, OPC (51339) / MONOLITHIC CONSTRUCTION & CONCRETE PRODUCTS, INC. · DPWH contractor code 5733
Contract amount:
₱147,161,959.05 (₱147.2M)
Funding source:
Regular Infra - GAA 2024 OO-2
Budget year:
2024
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GA0136 | Jul 22, 2025 | CONCRETING OF BRGY. SINGAY FMR, BRGY. SINGAY, MADALAG, AKLAN | On-Going | ₱14.9M |
| 25GA0067 | Feb 26, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT/EVACUATION CENTER), BARANGAY BALACTASAN, MADALAG, AKLAN | Completed | ₱4.9M |
| 25GA0068 | Feb 26, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT/EVACUATION CENTER), BARANGAY CABILAWAN, MADALAG, AKLAN | Completed | ₱4.9M |
| 25GA0073 | Feb 26, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT/EVACUATION CENTER), BARANGAY TALANGBAN, MADALAG, AKLAN | Completed | ₱4.9M |
| 24G00140 | Feb 20, 2025 | LGU HOSPITALS- MADALAG DISTRICT HOSPITAL, AKLAN | On-Going | ₱19.9M |
| 24GA0222 | Oct 15, 2024 | CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM, PROVINCE OF AKLAN | Completed | ₱2.9M |
| 24GA0093 | May 22, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, MADALAG, AKLAN | On-Going | ₱7.0M |
| 24GA0012 | Apr 22, 2024 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AKLAN RIVER, BRGY. POBLACION, MADALAG, AKLAN | Completed | ₱98.0M |