Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 24GA0007

DPWH infrastructure contract
Contract ID:
24GA0007
Fingerprint:
a6c8e7b4d50968…71d0086e9e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 28, 2024 (2 yrs 5 mo ago) · Target/actual end Aug 19, 2024
Description:
AKLAN EAST ROAD - K0321 + 344 - K0322 + 748
Category:
Roads
Implementing office:
DPWH Aklan DEO · Region VI
Contract amount:
₱30,895,420.19 (₱30.9M)
Funding source:
Regular Infra - GAA 2024 OO-1
Budget year:
2024

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GA0028Jun 10, 2025NRJ CABANGILA - SITIO EAHOG, BRGY. CATMON, ALTAVAS TO BRGY. AGKAWAYAN, MAMBUSAO, CAPIZ BOUNDARY ACCESS ROAD IN SUPPORT OF COCONUT PROCESSING FACILITY, FOOD PROCESSING, AND BANIG PRODUCTION, ALTAVAS, AKLANOn-Going₱21.7M
25GA0003Apr 10, 2025AKLAN EAST ROAD-K0310+335-K0310+406On-Going₱46.0M
25GA0016Apr 10, 2025AKLAN EAST RD - K0296 + 579 - K0296 + 800, K0297 + 340 - K0298 + 000, K0314 + 845 - K0315 + 911, K0318 + 185 - K0318 + 270, K0319 + 920 - K0321 + 000, K0322 + 748 - K0323 + 185Completed₱84.2M
25GA0009Mar 19, 2025AKLAN EAST RD - K0296+559 - K0296+561, K0309+747 - K0309+792, K0312+692 - K0312+810, K0313+406 - K0313+439, K0319+063 - K0319+115On-Going₱9.9M
25GA0049Mar 19, 2025CONSTRUCTION OF ROAD, SITIO KINABKABA, BARANGAY LUMAYNAY, ALTAVAS, AKLANCompleted₱4.9M
25GA0065Feb 26, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), DINAUT ELEMENTARY SCHOOL, BARANGAY MAN-UP, ALTAVAS, AKLANOn-Going₱4.9M
25GA0069Feb 26, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT/ EVACUATION CENTER), BARANGAY ODIONG, ALTAVAS, AKLANOn-Going₱4.9M
24G00119Nov 7, 2024LGU HOSPITALS-ALTAVAS DISTRICT HOSPITAL, AKLANOn-Going₱39.8M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.