Project 24GA0161

DPWH infrastructure contract
Contract ID:
24GA0161
Fingerprint:
a9136495aaa33e…652eec0e10 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 22, 2024 (2 yrs 5 mo ago) · Target/actual end Oct 22, 2024
Description:
REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG AKLAN EAST ROAD K0286+349 K0287+430, K0287+600 K0287+890, K0288+174 K0288+840, K0290+000 K0290+174, K0301+585 K0302+733, K0303+380 K0304+270, K0304+450 K0304+788, K0305+8
Category:
Roads
Implementing office:
DPWH Aklan DEO · Region VI
Contractor:
G.F. ROVERO MERCHANDISING · DPWH contractor code 27268
Contract amount:
₱137,440,984.93 (₱137.4M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
cbf2478c1b88…May 13, 2024DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AKLAN DEO₱135,999,902.18

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GA0047Feb 26, 2025CONSTRUCTION OF ROAD, SITIO CAEOG-A, BARANGAY CABUGAO, BATAN, AKLANOn-Going₱4.9M
25GA0075Feb 26, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY HEALTH CENTER, SITIO MAEOBOG, BARANGAY LALAB, BATAN, AKLANOn-Going₱4.9M
24GA0095Jul 4, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING, BATAN, AKLANOn-Going₱7.2M
24GA0228May 28, 2024CONSTRUCTION OF 2-STOREY 4-CLASSROOM SCHOOL BUILDING IN CAMALIGAN NATIONAL HIGH SCHOOL, BRGY. CAMALIGAN, BATAN, AKLANCompleted₱15.7M
24GA0029Mar 7, 2024CONSTRUCTION OF ROAD, SITIO PANDAN BARANGAY BAY-ANG, BATAN, AKLANCompleted₱4.0M
24GA0040Mar 7, 2024CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY MAGUBAHAY, BATAN, AKLANOn-Going₱2.9M
24GA0041Feb 6, 2024CONSTRUCTION (COMPLETION) OF MPB (COVERED COURT) BRGY. MAN-UP, BATAN, AKLANCompleted₱1.9M
23GA0192Sep 19, 2023CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS) PROVINCE OF AKLANCompleted₱2.3M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.