FY2026 GAA: ₱6.79T
PisoScan

Project 24GA0252

DPWH infrastructure contract
Contract ID:
24GA0252
Fingerprint:
fb07ab5e86c81b…5662fdd2d2 Verified
Status:
On-Going
Physical progress:
91.0%
Timeline:
Start Mar 19, 2025 (1 yr 7 mo ago)
Description:
CONSTRUCTION OF FLOOD CONTROL PROJECT ALONG AKLAN RIVER, BARANGAY DAJA SUR, BANGA, AKLAN
Category:
Flood Control and Drainage
Implementing office:
DPWH Aklan DEO · Region VI
Contractor:
MONOLITHIC CONSTRUCTION AND CONCRETE PRODUCTS, INC. · DPWH contractor code 5733
As listed: MONOLITHIC CONSTRUCTION & CONCRETE PRODUCTS, INC.
Contract amount:
₱19,249,995.35 (₱19.2M)
Funding source:
Outside Infra - Unprogrammed Appropriations 2024
Budget year:
2024

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
24GA0256Aug 7, 2025CONTINUING CONSTRUCTION/CONCRETING OF FARM TO MARKET ROAD AT SITIO KALINTAAN, BRGY. DAJA NORTE, BANGA, AKLANOn-Going₱14.9M
24GA0257Aug 7, 2025CONTINUING CONSTRUCTION/CONCRETING OF FARM TO MARKET ROAD AT BRGY. VENTURANZA TO BRGY. AGBANAWAN TO SITIO TAMPUEAW, BRGY. POLOCATE, BANGA, AKLANOn-Going₱14.9M
25GA0078May 23, 2025CONSTRUCTION OF ROAD, BARANGAY SIGCAY, BANGA, AKLANCompleted₱4.9M
25GA0079May 23, 2025CONSTRUCTION OF ROAD, BARANGAY TORRALBA, BANGA, AKLANCompleted₱4.9M
25GA0044Apr 3, 2025CONSTRUCTION OF ROAD, BARANGAY TABAYON, BANGA, AKLANOn-Going₱4.9M
25G00076Mar 24, 2025INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG AKLAN EAST RD- K0286+071- K0290+170On-Going₱47.8M
25GA0057Mar 19, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, SAMPAGUITA STREET, BARANGAY POBLACION, BANGA, AKLANOn-Going₱1.9M
25GA0019Mar 3, 2025REHABILITATION OF DIVERSION DAM OF AKLAN RIS AND BANK PROTECTION, AKLAN RIVER IRRIGATION SYSTEM, BANGA, AKLANOn-Going₱29.0M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.