FY2026 GAA: ₱6.79T
PisoScan

Project 24GB0157

DPWH infrastructure contract
Contract ID:
24GB0157
Fingerprint:
57b7f224d23951…863b8c3408 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 4, 2025 (1 yr 5 mo ago) · Target/actual end Sep 16, 2025
Description:
REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG SIBALOM RIVER, BRGY. BAGUMBAYAN, SAN REMIGIO, ANTIQUE (RE-BID)
Category:
Unprogrammed Appropriations 2024
Implementing office:
DPWH Antique DEO · Region VI
Contractor:
REVIM CONSTRUCTION · DPWH contractor code 52071
Contract amount:
₱10,403,683.95 (₱10.4M)
Funding source:
Outside Infra - Unprogrammed Appropriations 2024
Budget year:
2024

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GB0087Jun 20, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SIBALOM RIVER, SAN REMIGIO, ANTIQUE (PHASE 6)On-Going₱123.1M
25GB0070May 30, 2025PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - ODIONG - SIBALOM - SN REMIGIO - LEON RD - K0113+174 - K0117+000, ANTIQUEOn-Going₱113.8M
25GB0073May 30, 2025PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - BUGO - GEN FULLON RD - K0127+(-788) - K0127+036, K0129+503 - K0129+614, ANTIQUEOn-Going₱18.0M
24GB0158Mar 14, 2025REHABILITATION OF ODIONG-SIBALOM-SAN REMIGIO-LEON ROAD, K0120+460 - K0120+510, BRGY. CALAG-ITAN, SAN REMIGIO, ANTIQUEOn-Going₱10.1M
25G00065Mar 6, 2025SAN REMIGIO- BUGO- GEN FULLON- VALDERRAMA ROAD, ANTIQUEOn-Going₱149.1M
25GB0023Mar 4, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SINUNDULAN, SAN REMIGIO, ANTIQUECompleted₱4.9M
25GB0052Mar 4, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, SAN REMIGIO, ANTIQUEOn-Going₱7.2M
25GB0061Mar 4, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (MUNICIPAL BUILDING), BARANGAY POBLACION, SAN REMIGIO , ANTIQUEOn-Going₱9.9M