Project 24GH0181
DPWH infrastructure contract
Contract ID:
24GH0181
Fingerprint:
4d5aec82c16f07…d62d3d865b Verified
Status:
On-Going
Physical progress:
2.7%
Timeline:
Start Sep 12, 2024 (2 yrs 2 mo ago)
Description:
CONCRETING OF SITIO BAIRAN, BRGY. MALAYU-AN FMR, BRGY. MALAYU-AN, AJUY, ILOILO
Category:
Roads: Construction - PCCP, Roads: Construction - Slope Protection using Structural Measures (e.g. Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry)
Implementing office:
DPWH Iloilo 3rd DEO · Region VI
Contractor:
BRPRIME CONSTRUCTION SUPPLIES · DPWH contractor code 52736
Contract amount:
₱4,962,316.13 (₱5.0M)
Funding source:
Outside Infra - Roads: Construction - PCCP, Roads: Construction - Slope Protection using Structural Measures (e.g. Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry)
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| c77e9b0b188f… | Aug 20, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOILO 3RD DEO | ₱4,962,316.13 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GH0142 | May 26, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE- CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY MANGOROCORO, AJUY, ILOILO | On-Going | ₱143.6M |
| 25GH0144 | May 26, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE- CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY MANGOROCORO, AJUY, ILOILO | On-Going | ₱143.2M |
| 25GH0152 | May 26, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY AGNAGA, CONCEPCION, ILOILO | On-Going | ₱2.0M |
| 25GH0154 | Mar 27, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY LANJAGAN, AJUY, ILOILO | Completed | ₱3.0M |
| 25GH0156 | Mar 27, 2025 | CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY CULASI, AJUY, ILOILO | On-Going | ₱4.9M |
| 25GH0052 | Mar 26, 2025 | RECONSTRUCTION TO CONCRETE PAVEMENT- ILOILO EAST COAST CAPIZ RD K0231+714- K0232+939 | On-Going | ₱29.3M |
| 25GH0078 | Mar 26, 2025 | REHABILITATION/ MAJOR REPAIR OF BRIDGE - BALOGO BR. (B00211PN) ALONG ILOILO EAST COAST-CAPIZ RD | Completed | ₱11.4M |
| 25GH0110 | Mar 25, 2025 | REHABILITATION OF ROAD, BARANGAY BAY- ANG CONNECTING CEMPHIL CEMENT PRODUCTION PLANT, AJUY, ILOILO | On-Going | ₱57.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.