Project 24GP0079
DPWH infrastructure contract
Contract ID:
24GP0079
Fingerprint:
c9582e4b8eadb1…ef6cc3a6f1 Verified
Status:
On-Going
Physical progress:
98.7%
Timeline:
Start Sep 3, 2024 (2 yrs 2 mo ago)
Description:
CONCRETING OF BRGY. ROXAS FMR, BRGY. ROXAS, TAPAZ, CAPIZ
Category:
Roads
Implementing office:
DPWH Capiz 2nd DEO · Region VI
Contractor:
A.D. PENDON CONSTRUCTION & SUPPLY, INC. (FORMERLY: ADP CONSTRUCTION & SUPPLY) · DPWH contractor code 3466
Contract amount:
₱14,824,739.67 (₱14.8M)
Funding source:
Outside Infra - GAA 2024 DA FMR
Budget year:
2024
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GG0174 | Jun 6, 2025 | CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY GARANGAN, CALINOG, ILOILO | Completed | ₱3.4M |
| 25GP0059 | Jun 6, 2025 | REPAIR OF DAMAGED PIPE CULVERT STRUCTURE WITH REBLOCKING- TAPAZ- JAMINDAN- ALTAVAZ RD- K0091+505- K0091+555 | On-Going | ₱6.9M |
| 25GP0037 | Mar 26, 2025 | CONSTRUCTION OF CONCRETE ROAD - MAWANG TO BRGY. ARTUZ NRJ IN SUPPORT OF CACAO INDUSTRY PLANTATION, TAPAZ, CAPIZ | On-Going | ₱14.6M |
| 24GP0045 | Aug 13, 2024 | CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE- TAPAZ- JAMINDAN- ALTAVAZ RD- K0092+145- K0092+195 | On-Going | ₱24.5M |
| 24GP0062 | Apr 30, 2024 | CONSTRUCTION OF CONCRETE ROAD - BRGY. MAWANG TO BRGY. ARTUZ NRJ IN SUPPORT OF CACAO INDUSTRY PLANTATION, TAPAZ, CAPIZ | On-Going | ₱24.4M |
| 24GP0054 | Apr 11, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, TAPAZ CENTRAL ELEMENTARY SCHOOL, BRGY. POBLACION, TAPAZ, CAPIZ | On-Going | ₱4.8M |
| 24GP0056 | Apr 11, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING IN MUNICIPALITY OF TAPAZ, CAPIZ | Completed | ₱5.1M |
| 24GG0158 | Mar 8, 2024 | CONSTRUCTION OF MULTI - PURPOSE BUILDING, BARANGAY AGLONOK, CALINOG, ILOILO | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.