Project 24HC0064
DPWH infrastructure contract
Contract ID:
24HC0064
Fingerprint:
2423b9f44c3c14…a8cc4ae1e7 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 14, 2024 (2 yrs 5 mo ago) · Target/actual end Aug 27, 2024
Description:
CONCRETING OF BRGY. SAN MIGUEL TO BRGY. BABAG FMR, BRGY. SAN MIGUEL AND BRGY. BABAG, DAGOHOY, BOHOL
Category:
Roads
Implementing office:
DPWH Bohol 2nd DEO · Region VII
Contractor:
D' 5J CONSTRUCTION & SUPPLY · DPWH contractor code 48797
Contract amount:
₱14,914,310.76 (₱14.9M)
Funding source:
Outside Infra - GAA 2024 DA FMR
Budget year:
2024
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25HC0104 | Jul 3, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. POBLACION, DAGOHOY, BOHOL | Completed | ₱9.8M |
| 25HC0090 | Apr 2, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, DAGOHOY, BOHOL | Completed | ₱4.8M |
| 24HC0128 | Oct 3, 2024 | CONSTRUCTION (COMPLETION)/ REHABILITATION OF MULTI-PURPOSE BUILDINGS, DAGOHOY, BOHOL | Completed | ₱14.8M |
| 24HC0112 | Aug 15, 2024 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDINGS, DANAO, BOHOL | Completed | ₱9.9M |
| 24HC0090 | Jul 11, 2024 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. MAHAYAG, DAGOHOY, BOHOL | Completed | ₱2.0M |
| 24HC0100 | Jul 9, 2024 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. CAGAWASAN, DAGOHOY, BOHOL | Completed | ₱2.0M |
| 24HC0079 | Jun 24, 2024 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. VILLA AURORA, DAGOHOY, BOHOL | Completed | ₱2.0M |
| 24HC0083 | Jun 24, 2024 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. SAN VICENTE, DAGOHOY, BOHOL | Completed | ₱2.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.