Project 24HJ0097
DPWH infrastructure contract
Contract ID:
24HJ0097
Fingerprint:
87480121331c50…2cb74ac760 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 7, 2024 (2 yrs 8 mo ago) · Target/actual end Jun 24, 2024
Description:
CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-ROAD IMPROVEMENT OF AQUINO-QUEZON BOUNDARY ROAD, CANLAON CITY, NEGROS OR
Category:
Roads
Implementing office:
DPWH Negros Oriental 1st DEO · Negros Island Region
Contractor:
YCT BUILDERS CENTER COMPANY, INC. (FORMERLY YCT BUILDERS CENTER CO.) · DPWH contractor code 23830
Contract amount:
₱26,189,990.49 (₱26.2M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26RE0042 | Jul 13, 2026 | ROAD WIDENING ALONG BACOLOD-MURCIA-DS BENEDICTO-SN CARLOS CITY RD - K0069 + 571 - K0070 + 332 | On-Going | ₱32.3M |
| 26R00003 | Jun 25, 2026 | ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS : BACOLOD-MURCIA-DS BENEDICTO-SAN CARLOS CITY RD - K0064 + 289 - K0065 + 052, K0068 + 293 - K0069 + 571 | On-Going | ₱68.4M |
| 25RE0018 | Aug 19, 2025 | CONCRETING OF SITIO NAPATURAN, BRGY. CODCOD FMR, BRGY. CODCOD, SAN CARLOS CITY, NEGROS OCCIDENTAL | Completed | ₱19.8M |
| 25RE0015 | Jul 28, 2025 | CONSTRUCTION OF FLOOD MITIGATING STRUCTURE- MAGBABOY RIVER (UPSTREAM), SAN CARLOS CITY, NEGROS OCCIDENTAL | On-Going | ₱98.7M |
| 25RE0016 | Jul 28, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURES PALAMPAS RIVER, BARANGAY 1, SAN CARLOS CITY, NEGROS OCCIDENTAL | On-Going | ₱143.3M |
| 25GQ0053 | Jun 25, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURES AT KATINGAL-AN CREEK, ALONG BACOLOD NORTH ROAD RD (S00425NR), SAN CARLOS CITY, NEGROS OCCIDENTAL | Completed | ₱72.0M |
| 25GQ0052 | Jun 20, 2025 | ROAD WIDENING ALONG BACOLOD NORTH RD - K0160 + 133 - K0161 + 000 | On-Going | ₱27.4M |
| 25RE0009 | Jun 20, 2025 | CONSTRUCTION OF SCHOOL BUILDING, LAGHA ELEMENTARY SCHOOL MAIN, SITIO LAGHA, BARANGAY QUEZON, SAN CARLOS CITY, NEGROS OCCIDENTAL | Completed | ₱9.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.