Physical progress:
100%
Timeline:
Start Apr 11, 2024 (2 yrs 6 mo ago) · Target/actual end Jun 9, 2024
Description:
CONSTRUCTION OF POLO UNO ROAD, BARANGAY PUTONG, SAN JULIAN, EASTERN SAMAR
Category:
Roads
Implementing office:
DPWH Eastern Samar DEO · Region VIII
Contractor:
Contract amount:
₱6,929,666.74 (₱6.9M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| f5eeb1ddfa3a… | Mar 25, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - EASTERN SAMAR DEO | ₱6,900,874.24 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25IB0153 | Nov 12, 2025 | CONSTRUCTION OF ROAD, BARANGAY LIBAS, SAN JULIAN, EASTERN SAMAR | Completed | ₱4.9M |
| 25IB0025 | Feb 25, 2025 | CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS, SECONDARY ROADS, WRIGHT-TAFT-BORONGAN ROAD, K0919+052 - K0920+085 | Completed | ₱8.5M |
| 24IB0038 | Mar 18, 2024 | REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, LAYOG BR. (B00567SM), ALONG WRIGHT-TAFT-BORONGAN RD | Completed | ₱9.8M |
| 23IB0122 | Aug 10, 2023 | CONSTRUCTION OF 1STY2CL, PAGBABANGNAN ELEMENTARY SCHOOL, SAN JULIAN, EASTERN SAMAR | Completed | ₱5.0M |
| 23IB0120 | Aug 8, 2023 | CONSTRUCTION OF SOLAR WATER SYSTEM, SAN JULIAN, EASTERN SAMAR | Completed | ₱9.7M |
| 23IB0102 | Jun 14, 2023 | CONSTRUCTION OF ROAD, CASOROY - LAYOG, SAN JULIAN, EASTERN SAMAR | Completed | ₱9.8M |
| 23IB0104 | Jun 14, 2023 | CONSTRUCTION OF ACCESS ROAD, BARANGAY PUTONG TO BARANGAY LIBAS, SITIO MACAARONGON, BARANGAY LIBAS, SAN JULIAN, EASTERN SAMAR | Completed | ₱9.9M |
| 23IB0069 | May 4, 2023 | INSTALLATION OF SOLAR STREET LIGHTS ALONG WRIGHT-TAFT-BORONGAN RD, K0913+628 K0919+309 | Completed | ₱49.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.