Physical progress:
100%
Timeline:
Start Jul 15, 2024 (2 yrs 3 mo ago) · Target/actual end Sep 30, 2024
Description:
CONST. OF RAIN WATER COLLECTION SYSTEM (RWCS) AT: 1. TERAZA ELEMENTARY SCHOOL, BRGY. TERAZA, PALO, LEYTE; 2. CANHIDOC ELEM. SCHOOL, BRGY. CANHIDOC, PALO, LEYTE; 3. KAUSWAGAN NATIONAL HS, BRGY. BARAYONG, PALO, LEYTE; 4. TACURANGA ELEM. SCHOOL, BRGY. TACURA
Category:
Water Provision and Storage
Implementing office:
DPWH Leyte 1st DEO · Region VIII
Contractor:
JONI CONSTRUCTION · DPWH contractor code 26023
Contract amount:
₱2,885,199.00 (₱2.9M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| a534a5948f86… | Jul 3, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LEYTE 1ST ED | ₱2,885,199.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25IC0092 | Oct 9, 2025 | CONSTRUCTION OF BRIDGE, BARANGAY CAMIRE TO BARANGAY BALUD, TANAUAN, LEYTE | On-Going | ₱96.4M |
| 25IC0102 | Oct 8, 2025 | SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR LED STREET LIGHT ALONG PALO EAST BYPASS RD - CHAINAGE 0 - CHAINAGE 1534, LEYTE | On-Going | ₱29.4M |
| 25I00196 | Sep 12, 2025 | CLUSTER 2: 1. BUILDINGS AND OTHER STRUCTURES-MULTIPURPOSE/FACILITIES - NATIONAL BUILDING PROGRAM - CONSTRUCTION OF 4-STOREY DPWH REGIONAL OFFICE VIII BUILDING, PAWING, PALO, LEYTE; 2. BUILDINGS AND OTHER STRUCTURES-MULTIPURPOSE/FACILITIES - NATIONAL BUI | On-Going | ₱117.8M |
| 25IC0109 | Aug 14, 2025 | REHABILITATION OF ROAD, BARANGAY CANDAHUG, PALO, LEYTE | On-Going | ₱4.9M |
| 25IC0111 | Jul 31, 2025 | CONSTRUCTION OF ROAD, BARANGAY SAN JOSE, PALO, LEYTE | Completed | ₱4.9M |
| 24IC0140 | Jul 10, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL ANNEX II BUILDING) PALO, LEYTE | On-Going | ₱144.7M |
| 25I00048 | Jul 10, 2025 | ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - PALO - CARIGARA - ORMOC RD - K0919+205 - K0923+000, K0926+000 - K0929+980 | On-Going | ₱385.6M |
| 25IC0002 | Jun 30, 2025 | ASSET PRESERVATION - PREVENTIVE MAINTENANCE - SECONDARY ROADS - GOVERNMENT CENTER ROAD NETWORK - K0913 + 344.9 - K0913 + 705, BRGY, BARAS, PALO, LEYTE | On-Going | ₱14.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.