Project 24IE0009

DPWH infrastructure contract
Contract ID:
24IE0009
Fingerprint:
0a9febcf3e7aa0…49f3095be1 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 12, 2024 (2 yrs 8 mo ago) · Target/actual end Oct 24, 2024
Description:
ASSET PRESERVATION-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-TERTIARY ROADS, TABING-KAWAYAN-STA. ROSA-LAWIS-TABANGO RD., K1028+993 K1029+000, TABANGO, LEYTE
Category:
Roads
Implementing office:
DPWH Leyte 3rd DEO · Region VIII
Contract amount:
₱29,353,136.67 (₱29.4M)
Funding source:
Regular Infra - GAA 2024 OO-1
Budget year:
2024

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25IE0095Aug 4, 2025CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS), COLONIA ELEMENTARY SCHOOL, TABANGO, LEYTEOn-Going₱322.4K
25IE0060Jul 29, 2025CONSTRUCTION OF SITIO LIBUNGAO-SITIO TUBIG BAHO ROAD, BRGY. INANGATAN, TABANGO, LEYTECompleted₱9.9M
25IE0046Jul 17, 2025ASSET PRESERVATION REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE SECONDARY ROADS-CALUBIAN JCT. SAN ISIDRO-TABANGO-VILLABA-PALOMPON ROAD, K1037+425 K1037+571On-Going₱58.8M
25IE0068Jun 8, 2025CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY SANTA ROSA, TABANGO, LEYTEOn-Going₱4.9M
25IE0077May 29, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, PHASE 2, BARANGAY MANLAWAAN, TABANGO, LEYTECompleted₱2.0M
25IE0062May 26, 2025CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY TABING, TABANGO, LEYTEOn-Going₱4.9M
25IE0004Mar 24, 2025ASSET PRESERVATION-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDES-SECONDARY ROADS, CALUBIAN JCT-SN ISIDRO-TABANGO-VILLABA-PALOMPON RD K1026+968-K1027+039, K1037+000-K1037+072Completed₱24.4M
25IE0038Mar 10, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), MARCELINO R. VELOSO NATIONAL HIGH SCHOOL (MRVNHS), BARANGAY POBLACION, TABANGO, LEYTETABANGO, LEYTEOn-Going₱4.9M