Project 24IF0034
DPWH infrastructure contract
Contract ID:
24IF0034
Fingerprint:
3baf6171a8e006…cac7944831 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 13, 2024 (2 yrs 8 mo ago) · Target/actual end Apr 12, 2024
Description:
REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - VILLABA - PALOMPON RD - K1059+ (-90) - K1059+(-50)
Category:
Roads
Implementing office:
DPWH Leyte 4th DEO · Region VIII
Contractor:
MAVI CONSTRUCTION INC. · DPWH contractor code 50160
Contract amount:
₱2,881,902.41 (₱2.9M)
Funding source:
Regular Infra - GAA 2024 OO-1
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 2e51666f81d9… | Jan 30, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LEYTE 4TH DEO | ₱2,881,902.41 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26IF0018 | Jun 4, 2026 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - SAN MIGUEL BR. (B00203LT) ALONG LIBUNGAO-MATAG-OB-PALOMPON RD. | On-Going | ₱29.2M |
| 25IF0108 | Dec 15, 2025 | REPAIR/REHABILITATION OF CLASSROOMS, ALFREDO PARILLA NATIONAL HIGH SCHOOL, PALOMPON, LEYTE | Completed | ₱6.3M |
| 24I00415 | Aug 14, 2025 | CONSTRUCTION OF INNOVATION INCUBATION CENTER BUILDING - PALOMPON INSTITUTE OF TECHNOLOGY | On-Going | ₱34.6M |
| 25IF0090 | Jun 23, 2025 | CONCRETING OF BRGY. CADUHAAN TO MASABA FMR, PALOMPON, LEYTE | Completed | ₱29.8M |
| 25IF0087 | Jun 18, 2025 | CONCRETING OF BRGY. CATIGAHAN TO BRGY. SAN PABLO TO BRGY. SAN ROQUE FMR (PHASE II), BRGYS. CATIGAHAN, SAN PABLO AND SAN ROQUE, PALOMPON, LEYTE | On-Going | ₱23.9M |
| 25IF0083 | Jun 16, 2025 | CONCRETING OF BRGY. CAMBACBAC TO SITIO LUWAKAN FMR, BRGY. CAMBACBAC, PALOMPON, LEYTE | On-Going | ₱9.9M |
| 24IF0144 | Jun 9, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BELEN, PALOMPON, LEYTE | On-Going | ₱6.9M |
| 24I00336 | Nov 4, 2024 | COMPLETION ON THE REPAIR/REHABILITATION OF FASHION AND APPAREL TECHNOLOGY BUILDING, PIT MAIN CAMPUS, PALOMPON, LEYTE | On-Going | ₱7.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.