Project 24II0042
DPWH infrastructure contract
Contract ID:
24II0042
Fingerprint:
abb7d97cdfbdb3…01fc977396 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 17, 2024 (2 yrs 6 mo ago) · Target/actual end May 3, 2025
Description:
CONSTRUCTION/REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF LAS NAVAS FLOOD CONTROL STRUCTURES, CATUBIG RIVER BASINS, LAS NAVAS, NORTHERN SAMAR
Category:
Flood Control and Drainage
Implementing office:
DPWH Northern Samar 2nd DEO · Region VIII
Contractor:
JCL CONSTRUCTION AND SUPPLY · DPWH contractor code 50408
Contract amount:
₱24,260,606.51 (₱24.3M)
Funding source:
Regular Infra - GAA 2024 OO-2
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| aa5e18d9178b… | Apr 1, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NORTHERN SAMAR 2ND | ₱24,260,606.51 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26II0011 | Jul 29, 2026 | REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS, TERTIARY ROADS, ARTECHE-JIPAPAD-LAS NAVAS-RAWIS RD, K0813+952 - K0814+800, NORTHERN SAMAR, 2ND DISTRICT | On-Going | ₱97.2M |
| 25II0064 | Jun 26, 2026 | CONSTRUCTION OF CLASSROOMS, LAS NAVAS NATIONAL HIGH SCHOOL, LAS NAVAS, NORTHERN SAMAR | On-Going | ₱16.9M |
| 25II0012 | Nov 10, 2025 | CONSTRUCTION OF MISSING LINKS/NEW ROADS, ARTECHE, BRGY. CATUMSAN-JIPAPAD-LAS NAVAS-CATUBIG-RAWIS ROAD, NORTHERN SAMAR SIDE, NORTHERN SAMAR 2ND DISTRICT. | On-Going | ₱87.9M |
| 25II0059 | Sep 16, 2025 | CONSTRUCTION OF SCHOOL BUILDING, SAN ISIDRO NATIONAL HIGH SCHOOL, BRGY. SAN ISIDRO, LAS NAVAS, NORTHERN SAMAR | Completed | ₱10.0M |
| 25II0028 | Jun 9, 2025 | CONSTRUCTION OF ROAD, SILVINO LUBOS - LAS NAVAS ROAD, NORTHERN SAMAR, NORTHERN SAMAR 2ND DISTRICT | On-Going | ₱68.7M |
| 25II0024 | Apr 16, 2025 | ACCCES ROAD LEADING TO PINIPISAKAN FALLS, LAS NAVAS, NORTHERN SAMAR | On-Going | ₱39.2M |
| 25II0023 | Apr 8, 2025 | CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, REHAB. OF LAS NAVAS FLOOD CONTROL STRUCTURE AND DRAINAGE SYSTEM, CATUBIG RIVER BASIN, LAS NAVAS, NORTHERN SAMAR | Completed | ₱34.3M |
| 25II0027 | Apr 8, 2025 | CONSTRUCTION OF ROAD, GANDARA - MATUGUINAO - LAS NAVAS ROAD (NORTHERN SAMAR SIDE) | On-Going | ₱78.1M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.