Project 24J00097
DPWH infrastructure contract
Contract ID:
24J00097
Fingerprint:
c33bff578fc207…f23f5b8ede Verified
Status:
On-Going
Physical progress:
94.5%
Timeline:
Start May 3, 2024 (2 yrs 6 mo ago)
Description:
REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - TUNGUSONG-TUBIG INDANGAN RD - CHAINAGE 4000 - CHAINAGE 8470
Category:
Roads
Implementing office:
DPWH Region IX · Region IX
Contractor:
JAMARI CONSTRUCTION (FORMERLY FRAE CONSTRUCTION) (21580) / ZAMBO J.A. BUILDERS · DPWH contractor code 40678
Contract amount:
₱144,009,654.76 (₱144.0M)
Funding source:
Regular Infra - GAA 2024 OO-1
Budget year:
2024
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 23J00124 | Apr 17, 2023 | PAVING OF UNPAVED ROADS - TERTIARY ROADS TONGUSONG - TUBIG - INDANGAN - (SO0008TW) | Completed | ₱149.0M |
| 22J00114 | Feb 22, 2022 | PREVENTIVE MAINTENANCE - TERTIARY ROADS TUNGUSONG -TUBIG INDANGAN ROAD | On-Going | ₱58.4M |
| 20J00115 | Jun 26, 2020 | WIDENING OF PERMANENT BRIDGES - TONGGUSONG BRIDGE ALONG TONGGUSONG - TUBIG INDANGAN NATIONAL ROAD | On-Going | ₱38.2M |
| 20J00106 | May 28, 2020 | CONSTRUCTION OF MISSING LINKS TONGGUSONG TUBIG INDANGAN NATIONAL ROAD, SIMUNUL, TAWI TAWI | On-Going | ₱36.8M |
| 17J00178 | Feb 20, 2018 | WIDENING OF BRIDGE APPROACH AND CAUSEWAY IMPROVEMENT OF BRIDGE APPROACH CAUSEWAY ALONG NATIONAL ROAD, SIMUNUL CIRCUMFERENTIAL NATIONAL ROAD, TAWI TAWI, STA. 14+844.00 TO STA. 15+002, NET LENGTH: 158.00 LN.M. | Completed | ₱37.2M |
| 17J00179 | Feb 20, 2018 | WIDENING OF BRIDGE APPROACH AND CAUSEWAY IMPROVEMENT OF BRIDGE APPROACH CAUSEWAY ALONG NATIONAL ROAD, SIMUNUL CIRCUMFERENTIAL NATIONAL ROAD, TAWI TAWI, STA. 15+200 TO STA. 15+331.00, NET LENGTH: 131.00 LN.M. | Completed | ₱27.9M |
| 17J00180 | Feb 20, 2018 | CONCRETING OF SIMUNUL CIRCUMFERENTIAL NATIONAL ROAD, TONGGUSONG TUBIG, INDANGAN ROAD SECTION, TAWI TAWI LONE DISTRICT, STA. 16+062.00 TO STA. 16+713.00, NET LENGTH: 651.00 LN.M./0.651 KM/1.30 LANE KM | Completed | ₱23.3M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.