Project 24J00279
DPWH infrastructure contract
Contract ID:
24J00279
Fingerprint:
dd0760e367f83b…1d8e3efb79 Verified
Status:
On-Going
Physical progress:
100%
Timeline:
Start Dec 11, 2024 (1 yr 11 mo ago)
Description:
IMPLEMENTATION AND MONITORING OF PAMANA PROJECT - CONSTRUCTION OF WATER SYSTEM LEVEL II, BRGY. KAGAY, SULU
Category:
Water Provision and Storage
Implementing office:
DPWH Region IX · Region IX
Contractor:
AHSB CONSTRUCTION · DPWH contractor code 55648
Contract amount:
₱9,945,003.20 (₱9.9M)
Funding source:
Outside Infra - PAMANA 2024
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| a51acb884f2b… | Dec 6, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION IX | ₱9,945,003.20 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 24J00275 | Nov 8, 2024 | CONSTRUCTION OF KAGAY - SAWAKI - BUDTARAN - HUGPONG ROAD, SULU | On-Going | ₱69.6M |
| 24J00276 | Nov 8, 2024 | CONSTRUCTION OF KAGAY TO MALIMBAYA ROAD, INDANAN, SULU | On-Going | ₱49.7M |
| 24J00182 | May 3, 2024 | IMPROVEMENT OF ROADS, MAIMBUNG AND INDANAN ROADS, SULU | On-Going | ₱49.5M |
| 24J00189 | May 3, 2024 | REHABILITATION OF JUNCTION TIMBANGAN - ROMANDIER ROAD | On-Going | ₱49.5M |
| 24J00075 | Mar 25, 2024 | REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - JOLO - INDANAN - PARANG - SILANGKAN ROAD - CHAINAGE 11660 - CHAINAGE 12740 | On-Going | ₱48.2M |
| 22J00129 | Jun 24, 2022 | REHABILITATION OF ROAD, JOLO - BATOBATO - SILANGKAN ROAD, JOLO- INDANAN, SULU | Completed | ₱144.7M |
| 22J00096 | Mar 26, 2022 | ROAD WIDENING - SECONDARY ROADS - JOLO-INDANAN-PARANG-SILANGKAN ROAD (PACKAGE 2) | On-Going | ₱116.9M |
| 22J00097 | Mar 26, 2022 | ROAD WIDENING - SECONDARY ROADS - JOLO-INDANAN-PARANG-SILANGKAN ROAD (PACKAGE 3) | Completed | ₱32.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.