Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 24JB0027

DPWH infrastructure contract
Hashed input (canonical JSON of the source row)
["dpwh","24JB0027","CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LAYAWAN RIVER ( BATOTILTIL SECTION) ALONG DIPOLOG-PUNTA-DANSULLAN-S. OSMEÑA-ZAMBOANGA DEL NORTE/SUR BDRY ROAD, SERGIO OSMEÑA, ZN","Flood Control and Drainage","On-Going",20352970.94,0,100,"Zamboanga del Norte 1st DEO","Region IX","ESR CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY: ESR CONSTRUCTION & SUPPLIES) (10451)","2024-01-30",null,2024,"Regular Infra - GAA 2024 OO-2",8.31422,123.47985,"907214000","907200000"]
SHA-256
05ef2da678d3c80619c9d756eecfbc64232ea1f8498437b891d5f12922d54207

Hash the line above with SHA-256 to reproduce the fingerprint. It proves the record is unchanged since import. It is not a blockchain entry, and it cannot prove the source data is accurate.