Project 24JE0006
DPWH infrastructure contract
Contract ID:
24JE0006
Fingerprint:
d3ec7fdf58b562…ef267eac6a Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 19, 2024 (2 yrs 8 mo ago) · Target/actual end Jun 17, 2024
Description:
BASIC INFRASTRUCTURE PROGRAM CONSTRUCTION OF ROAD, BARANGAY LIBERTAD TO BARANGAY POBLACION MUNICIPALITY OF SOMINOT, ZAMBOANGA DEL SUR
Category:
Roads
Implementing office:
DPWH Zamboanga del Sur 1st DEO · Region IX
Contractor:
NRMM CONSTRUCTION AND DEV'T CORP. · DPWH contractor code 41172
Contract amount:
₱9,894,937.24 (₱9.9M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25JE0018 | Feb 14, 2025 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) CONSTRUCTION OF ROAD, NRJ BARANGAY POBLACION- BARANGAY LIBERTAD- BARANGAY SANTO NIÑO- BARANGAY LUMANGOY- BARANGAY SAWA- BARANGAY BINAYAN, LABANGAN AND SOMINOT, ZAMBOANGA DEL SUR | Completed | ₱29.4M |
| 24JE0077 | Jul 1, 2024 | CONSTRUCTION OF 1 STOREY 2 CLASSROOM SCHOOL BUILDING IN BAG-ONG BAROY ELEMENTARY SCHOOL, BARANGAY BAG- ONG BAROY, MUNICIPALITY OF SOMINOT, ZAMBOANGA DEL SUR | Completed | ₱5.0M |
| 23JE0088 | Oct 10, 2023 | CONSTRUCTION OF 1 STOREY 3 CLASSROOM (1STY3CL) WITH TOILET, SOMINOT CES- SPED, SOMINOT, ZAMBOANGA DEL SUR | Completed | ₱5.3M |
| 23JE0090 | Oct 10, 2023 | CONSTRUCTION OF 1 STOREY 2 CLASSROOM (1STY2CL) WITH TOILET, PICTORAN ES, SOMINOT, ZAMBOANGA DEL SUR | Completed | ₱3.9M |
| 23JE0091 | Oct 10, 2023 | CONSTRUCTION OF 1 STOREY 2 CLASSROOM (1STY2CL) WITH TOILET, SUBANEN AGRICULTURAL NHS, SOMINOT, ZAMBOANGA DEL SUR | Completed | ₱4.0M |
| 23J00089 | Jul 21, 2023 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - SOMINOT -DUMINGAG ROAD, ZAMBOANGA DEL SUR | On-Going | ₱38.7M |
| 23J00090 | Jul 21, 2023 | CONSTRUCTION OF BYPASS AND DIVERSION ROADS - SOMINOT - MAHAYAG ROAD, ZAMBOANGA DEL SUR | Completed | ₱48.2M |
| 23JE0055 | Mar 31, 2023 | BASIC INFRASTRUCTURE PROGRAM (BIP) CONSTRUCTION OF ROAD, BRGY. LIBERTAD, SOMINOT, ZAMBOANGA DEL SUR | Completed | ₱9.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.