Project 24JJ0020

DPWH infrastructure contract
Contract ID:
24JJ0020
Fingerprint:
c1f97e45c56c19…519705da64 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 27, 2024 (2 yrs 7 mo ago) · Target/actual end Aug 6, 2025
Description:
REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2104 + 831 - K2104 + 906, K2105 + 393 - K2105 + 447
Category:
Roads
Implementing office:
Contractor:
LONG ISLAND BUILDERS & CONSTRUCTION · DPWH contractor code 31730
Contract amount:
₱49,000,000.00 (₱49.0M)
Funding source:
Regular Infra - GAA 2024 OO-1
Budget year:
2024

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
a7e7bb94514a…Mar 8, 2024DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ZAMBOANGA DEL NORT₱48,261,467.14

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25JJ0002Mar 27, 2025PREVENTIVE MAINTENANCE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2096 + (-507) - K2096 + (-040), K2096 + (-011) - K2097 + 522)Completed₱33.3M
25JJ0020Mar 14, 2025ROAD WIDENING - SECONDARY ROADS, SIOCON-SIRAWAI RD - K2091+400 K2094+000On-Going₱82.7M
25JJ0030Feb 24, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT PIACAN RIVER, BARANGAY PIACAN, SIRAWAI, ZAMBOANGA DEL NORTECompleted₱44.1M
25JJ0037Feb 24, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY TAPANAYAN, SIRAWAI, ZAMBOANGA DEL NORTECompleted₱2.0M
24JJ0045Jun 7, 2024CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS) AT 1. BULACAN, SIOCON, ZN 2. MAKIANG, SIOCON, ZN 3. MAMAD, BALIGUIAN, ZN 4. MAMAWAN, BALIGUIAN, ZN 5. SAN JOSE, BALIGUIAN, ZN 6. SIAY, SIOCON, ZN 7. SIRAWAI, ZAMBOANGA DEL NORTECompleted₱2.9M
24JJ0008Feb 14, 2024PREVENTIVE MAINTENANCE - SECONDARY ROADS, SIOCON- SIRAWAI- SIBUCO- LIMPAPA RD- K2098 + 000 - K2102 + 300Completed₱118.9M
24JJ0031Feb 14, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PULA BATO, SIRAWAI, ZAMBOANGA DEL NORTECompleted₱5.0M
23JJ0044Feb 7, 2024CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE ALONG SIOCON-SIRAWAI RD (S01147MN), K2088+875 - K2089+043, K2093+095 - K2093+155Completed₱61.8M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.