Project 24K00442
DPWH infrastructure contract
Contract ID:
24K00442
Fingerprint:
e4a1535c4961a8…d37a92a446 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 23, 2024 (2 yrs 2 mo ago) · Target/actual end Feb 18, 2025
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING, PUROK 4, BARANGAY WEST POBLACION, KALILANGAN, BUKIDNON
Category:
GAA 2024 SSP
Implementing office:
DPWH Region X · Region X
Contractor:
STPK CONSTRUCTION SERVICES · DPWH contractor code 45905
Contract amount:
₱9,854,717.28 (₱9.9M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| b9c058e8cc0d… | Aug 6, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION X | ₱9,854,717.28 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25KN0064 | Feb 16, 2026 | CONSTRUCTION OF CLASSROOMS, PASAYANON ES, KALILANGAN, BUKIDNON | On-Going | ₱2.9M |
| 25KN0065 | Feb 16, 2026 | CONSTRUCTION OF SCHOOL HEALTH FACILITIES, KALILANGAN CES, KALILANGAN, BUKIDNON | Completed | ₱2.9M |
| 25K00426 | Jul 11, 2025 | CONSTRUCTION OF ONE (1) UNIT 4-STOREY 12 DOORS QUARTERING FACILITY FOR OFFICER'S QUARTERS | On-Going | ₱111.3M |
| 25K00427 | Jul 11, 2025 | CONSTRUCTION OF ONE (1) UNIT 4-STOREY 12 DOORS QUARTERING FACILITY FOR ENLISTED PERSONNEL | On-Going | ₱85.7M |
| 25K00243 | May 30, 2025 | PREVENTIVE MAINTENANCE-SECONDARY RODS, BUKIDNON BDRY-NORTH COTABATO RD (S01606MN) - CHAINAGE 0 - CHAINAGE 10000 | On-Going | ₱235.4M |
| 25KN0052 | May 23, 2025 | CONCRETING OF SITIO DARUSALAM, BRGY. NINOY AQUINO FMR, BRGY. NINOY AQUINO, KALILANGAN, BUKIDNON | On-Going | ₱14.6M |
| 25KN0009 | Mar 26, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BARORAWON, KALILANGAN, BUKIDNON | On-Going | ₱12.9M |
| 25KN0042 | Mar 25, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BANGBANG, KALILANGAN, BUKIDNON | On-Going | ₱12.6M |