Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 24KE0103

DPWH infrastructure contract
Contract ID:
24KE0103
Fingerprint:
9b6f6174de0653…693b2137cf Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 12, 2024 (2 yrs 4 mo ago) · Target/actual end Feb 26, 2025
Description:
CONCRETING OF SITIO ABU BAYLAO TO SITIO BINUNSARAN, POBLACION FMR, MAMBAJAO, CAMIGUIN
Category:
Roads
Implementing office:
DPWH Camiguin DEO · Region X
Contract amount:
₱14,474,227.06 (₱14.5M)
Funding source:
Outside Infra - GAA 2024 DA FMR
Budget year:
2024

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
3fcc04187027…Jun 27, 2024DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAMIGUIN DEO₱14,474,227.06

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26KE0004Jul 30, 2026REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-SECONDARY ROADS - CAMIGUIN CIRCUMFERENTIAL ROAD - K0005 + 934 - K0006 + 034On-Going₱8.7M
25KE0061Feb 10, 2026REPAIR/REHABILITATION OF 2 CLASSROOMS, BINUNSARAN ELEMENTARY SCHOOL, MAMBAJAO, CAMIGUINOn-Going₱1.3M
25KE0065Feb 10, 2026RESTORATION AND CONSERVATION OF GABALDON AND OTHER HERITAGE SCHOOL BUILDING, KUGUITA INTEGRATED SCHOOL, MAMBAJAO, CAMIGUINOn-Going₱4.5M
25KE0060Nov 6, 2025CONSTRUCTION OF SCHOOL BUILDING, MAGTING ELEMENTARY SCHOOL, MAGTING, MAMBAJAO, CAMIGUINOn-Going₱12.7M
25KE0038Sep 29, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING INCLUDING SITE DEVELOPMENT, BOARDWALK AND LANDSCAPING BARANGAY POBLACION, MAMBAJAO, CAMIGUINOn-Going₱49.2M
25KE0039Sep 29, 2025CONSTRUCTION OF BOARDWALK WITH VIEW DECK (OLD WHARF), PHASE II, MUNICIPAL PLAZA, BARANGAY POBLACION, MAMBAJAO, CAMIGUINOn-Going₱49.2M
25KE0017Jun 12, 2025CONSTRUCTION OF ROADS, BARANGAYS AGOHO, BUG-ONG AND MAGTING, MAMBAJAO, CAMIGUINOn-Going₱9.6M
25KE0041Jun 3, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) SITIO BINUNSARAN, MAMBAJAO, CAMIGUINOn-Going₱9.8M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.