DPWH infrastructure contract
Contract ID:
24KG0034
Fingerprint:
24e062202bbd22…8c3a0e08fd Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 20, 2024 (2 yrs 5 mo ago) · Target/actual end Oct 16, 2024
Description:
INSTALLATION OF ROADWAY LIGHTING STRUCTURES ALONG LINAMON-ZAMBOANGA NATIONAL HIGHWAY, MAIGO, LANAO DEL NORTE
Category:
Roads
Implementing office:
Contractor:
MEGALINE BUILDERS AND SUPPLY · DPWH contractor code 37952
Contract amount:
₱9,652,828.50 (₱9.7M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
1e01f780dfd8…May 14, 2024DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LANAO DEL NORTE 2N₱9,652,828.50

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26KG0027Jun 10, 2026CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG LINAMON-ZAMBOANGA RD-K1562+460-K1562+532, K1562+744-K1563+000On-Going₱3.4M
25KG0012Mar 19, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MAIGO BRIDGE (BO0949MN), PACKAGE 1, MAIGO, LANAO DEL NORTEOn-Going₱48.4M
25KG0002Jan 21, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY MENTERING, MAIGO, LANAO DEL NORTECompleted₱5.8M
25KG0003Jan 21, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY KULASIHAN, MAIGO, LANAO DEL NORTECompleted₱5.8M
25KG0006Jan 21, 2025CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONE, SEGAPOD TO MALIWANAG ROAD CONNECTING NATIONAL HIGHWAY OF SEGAPOD IN SUPPORT TO COCONUT OIL RUBBER AND TABLEA PROCESSING INDUSTRY, MAIGO, LANAO DEL NORTECompleted₱14.5M
25KG0032Jan 21, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (PHASE II), BARANGAY POBLACION, MAIGO, LANAO DEL NORTECompleted₱29.4M
24K00468Nov 25, 2024CONSTRUCTION OF MSU-MSAT SPORTS DEVELOPMENT CENTER (PHASE II), MAIGO, LANAO DEL NORTE -MINDANAO STATE UNIVERSITYOn-Going₱29.6M
24K00173May 3, 2024REPLACEMENT OF PERMANENT WEAK BRIDGE-MAIGO BR. (B00949MN) ALONG LINAMON-ZAMBOANGA RDOn-Going₱146.4M