Contract ID:
24LA0143
Fingerprint:
33226c69e107c6…c89c7ef6cf Verified
Status:
On-Going
Physical progress:
84.6%
Timeline:
Start Mar 10, 2025 (1 yr 8 mo ago)
Description:
ROAD CONCRETING SITIO VACA TO NEW SLAUGHTERHOUSE TO PANGIBIRAN, MABINI, DAVAO DE ORO, PHASE 2
Category:
Roads
Implementing office:
DPWH Davao de Oro 1st DEO · Region XI
Contractor:
UP SCALE BUILDERS AND SUPPLY CORP. · DPWH contractor code 48939
Contract amount:
₱13,754,683.73 (₱13.8M)
Funding source:
Outside Infra - Unprogrammed Appropriations 2024
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| caf9e44d1ffa… | Feb 25, 2025 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - DAVAO DE ORO 1ST D | ₱13,754,683.73 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25LA0076 | Aug 8, 2025 | CONSTRUCTION OF (COMPLETION) MULTI-PURPOSE BUILDING, BARANGAY ANITAPAN NATIONAL HIGH SCHOOL, MABINI, DAVAO DE ORO | On-Going | ₱3.0M |
| 25LA0083 | Jul 24, 2025 | CONSTRUCTION OF MULTI PURPOSE BUILDING, BARANGAY GOLDEN VALLEY, MABINI, DAVAO DE ORO | On-Going | ₱4.7M |
| 25LA0090 | Jul 24, 2025 | CONSTRUCTION OF ROAD, MANANGCOL, GOLDEN VALLEY - ANITAPAN, MABINI, DAVAO DE ORO | On-Going | ₱34.3M |
| 25LA0070 | May 23, 2025 | CONSTRUCTION OF REVETMENT ALONG TUNGA CREEK, MABINI, DAVAO DE ORO | On-Going | ₱96.5M |
| 24LA0142 | Mar 10, 2025 | ROAD CONCRETING FROM CADUNAN NATIONAL HIGHWAY TO NEW MABINI SANITARY LANDFILL SITE MABINI, DAVAO DE ORO, PHASE 2 | On-Going | ₱9.4M |
| 24L00336 | Jan 20, 2025 | REHABILITATION/RECONSTRUCTION OF REVETMENT FLOOD MITIGATION STRUCTURE ALONG TAGBALAOBAO RIVER LOCATED AT PUROKS MADRE DE CACAO, MABOLO, NARRA, AND MAHOGANY, BRGY. PINDASAN, MABINI, DAVAO DE ORO | On-Going | ₱42.9M |
| 24L00338 | Jan 20, 2025 | REHABILITATION/RECONSTRUCTION OF REVETMENT FLOOD MITIGATION STRUCTURE ALONG TAGBALAOBAO RIVER LOCATED AT PUROK PARK B-2 AND RIVERSIDE, BRGY. PINDASAN, MABINI, DAVAO DE ORO | Completed | ₱42.2M |
| 24LA0113 | Aug 9, 2024 | CONCRETING OF BRGY. GOLDEN VALLEY FMR, BRGY. GOLDEN VALLEY, MABINI, DAVAO DE ORO | Completed | ₱14.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.