Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 24LD0015

DPWH infrastructure contract
Contract ID:
24LD0015
Fingerprint:
ff4b0e6a4a3463…84e0637014 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 6, 2024 (2 yrs 6 mo ago) · Target/actual end Dec 10, 2024
Description:
WIDENING OF BRIDGE - MANAGA PARALLEL BR. (B01999MN) ALONG DAVAO-COTABATO RD (JCT DIGOS-COTABATO SECTION), DAVAO DEL SUR
Category:
GAA 2024 OO-1
Implementing office:
Contractor:
TKS BUILDERS & SUPPLIES · DPWH contractor code 23415
Contract amount:
₱67,550,000.00 (₱67.5M)
Funding source:
Regular Infra - GAA 2024 OO-1
Budget year:
2024

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
509bdad90170…Apr 23, 2024DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - DAVAO DEL SUR DIST₱65,522,742.90

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25LD0193Feb 23, 2026PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY- DAVAO- COTABATO ROAD (JCT. DIGOS- COTABATO SECTION)-K1575+035-K1575+322, K1582+670-, K1582+714, K1592+100-K1592+1078, DAVAO DEL SUROn-Going₱94.8M
25LD0202Sep 22, 2025PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-DAVAO-COTABATO RD (JCT DIGOS-COTABATO SECT.)-K1579+093-K1580+625, DAVAO DEL SURCompleted₱95.9M
25LD0203Sep 22, 2025PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY- DAVAO- COTABATO ROAD (JCT. DIGOS- COTABATO SECTION)- K1572+000-K1573+032, K1575+322-K1575+565, DAVAO DEL SURCompleted₱96.1M
25LD0157Jun 25, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE-CONCRETE REVETMENT AT MATANAO RIVER ALONG MATANAO NHS LEFT SIDE DOWNSTREAM SECTION PHASE I, MATANAO, DAVAO DEL SUROn-Going₱122.8M
25LD0205Jun 3, 2025CONSTRUCTION OF EVACUATION CENTER, BARANGAY SAN VICENTE, MATANAO, DAVAO DEL SURCompleted₱4.8M
25LD0018Mar 26, 2025PREVENTIVE MAINTENANCE OF ROAD; ASPHALT OVERLAY- DAVAO- COTABATO RD (JCT DIGOS-COTABATO SECT)-K1575+565-K1576+140, K1582+714-K1582+844, K1585+241-K1585+700, DAVAO DEL SUROn-Going₱96.3M
25LD0056Mar 26, 2025CONSTRUCTION OF ROAD, CENTRO KIBAO TO PUROK 3, BARANGAY KIBAO, MATANAO, DAVAO DEL SUROn-Going₱19.8M
25LD0206Mar 26, 2025CONCRETING OF BRGY. CAMANCHILES FMR, BRGY. CAMANCHILES, MATANAO, DAVAO DEL SURCompleted₱14.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.