Project 24LD0141
DPWH infrastructure contract
Contract ID:
24LD0141
Fingerprint:
2a7c85891c3f8a…55a4d4e575 Verified
Status:
On-Going
Physical progress:
100.0%
Timeline:
Start Jul 16, 2024 (2 yrs 3 mo ago)
Description:
PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-DAVAO-COTABATO RD (JCT. DIGOS- COTABATO SECT)- K1585+700-K1586+945, DAVAO DEL SUR
Category:
Roads
Implementing office:
DPWH Davao del Sur DEO · Region XI
Contractor:
P.L. SEBASTIAN CONSTRUCTION, INC. (FORMERLY: P.L. SEBASTIAN CONSTRUCTION) · DPWH contractor code 35840
Contract amount:
₱71,287,786.71 (₱71.3M)
Funding source:
Regular Infra - GAA 2024 OO-1
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| d182a77808d3… | Jul 3, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - DAVAO DEL SUR DIST | ₱71,287,786.71 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25LD0194 | Sep 22, 2025 | PREVENTIVE MAINTENANCE OF ROAD;: ASPHALT OVERLAY- DAVAO- COTABATO ROAD (JCT. DIGOS-COTABATO SECTION)-K1580+625-K1581+434, K1582+118-K1582+670, DAVAO DEL SUR | Completed | ₱96.5M |
| 25LD0170 | Jul 22, 2025 | CONSTRUCTION OF ROAD, BRGY. SIBAYAN, MUNICIPALITY OF BANSALAN, DAVAO DEL SUR | Completed | ₱4.8M |
| 25LD0169 | Jun 25, 2025 | CONSTRUCTION OF CONCRETE REVETMENT/DIKE AT BARANGAY RIZAL, BANSALAN, DAVAO DEL SUR | Completed | ₱99.0M |
| 25LD0186 | Jun 25, 2025 | CONSTRUCTION OF ROAD AT BARANGAY DOLO, BANSALAN, DAVAO DEL SUR | Completed | ₱4.8M |
| 24LD0215 | May 28, 2025 | CONCRETING OF FMR LOCATED AT BARANGAY LINAWAN, BANSALAN, DAVAO DEL SUR | Completed | ₱9.9M |
| 25LD0105 | Mar 24, 2025 | CONSTRUCTION OF SK FEDERATION MPB, PROVINCIAL CAPITOL, MATTI, DIGOS CITY, DAVAO DEL SUR | On-Going | ₱4.8M |
| 25LD0106 | Mar 24, 2025 | CONSTRUCTION OF MPB, BRGY. DOLO, BANSALAN, DAVAO DEL SUR | Completed | ₱4.8M |
| 25LD0123 | Mar 24, 2025 | CONSTRUCTION OF MULTIPURPOSE BUILDING, BRGY. DARAPUAY, BANSALAN, DAVAO DEL SUR | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.