Project 24NF0022
DPWH infrastructure contract
Contract ID:
24NF0022
Fingerprint:
db8f22ce2e0684…8e0e9094aa Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 26, 2024 (2 yrs 7 mo ago) · Target/actual end Aug 22, 2024
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY NUEVO CAMPO, SAN BENITO, SURIGAO DEL NORTE
Category:
Buildings and Facilities
Implementing office:
DPWH Surigao del Norte 1st DEO · Region XIII
Contractor:
RADIAN CONSTRUCTION AND SUPPLY · DPWH contractor code 43184
Contract amount:
₱4,948,027.00 (₱4.9M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 3b72e1df2d6f… | Mar 23, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SURIGAO DEL NORTE | ₱4,948,027.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25NF0040 | Jul 18, 2025 | REHABILITATION OF MULTI-PURPOSE BUILDING (MUNICIPAL GYMNASIUM) BARANGAY TALISAY, SAN BENITO, SURIGAO DEL NORTE | Completed | ₱9.8M |
| 25NF0082 | Jun 27, 2025 | CONSTRUCTION/ COMPLETION OF MULTI PURPOSE BUILDING, BARANGAY SAN JUAN, SAN BENITO, SURIGAO DEL NORTE | Completed | ₱4.9M |
| 25NF0069 | Mar 28, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BONGDO, SAN BENITO, SURIGAO DEL NORTE | Completed | ₱4.9M |
| 24NF0066 | May 31, 2024 | CONSTRUCTION OF MULTI-PURPOSE FACILITY, BRGY. TALISAY, SAN BENITO, SIARGAO ISLAND, SURIGAO DEL NORTE | Completed | ₱9.8M |
| 24N00129 | May 16, 2024 | CONSTRUCTION OF SHORE PROTECTION STRUCTURE ALONG BRGY. TALISAY, SAN BENITO, SURIGAO DEL NORTE | Completed | ₱99.0M |
| 24N00122 | Apr 8, 2024 | CONSTRUCTION OF SHORE STRUCTURE, BRGY. TALISAY, SAN BENITO, SURIGAO DEL NORTE | Completed | ₱48.2M |
| 24NF0038 | Apr 5, 2024 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG JCT. SAN BENITO - STA. MONICA ROAD, SAN BENITO, SURIGAO DEL NORTE | Completed | ₱39.5M |
| 24NF0020 | Feb 7, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY BONGDO, SAN BENITO, SURIGAO DEL NORTE | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.