Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 24OB0077

DPWH infrastructure contract
Contract ID:
24OB0077
Fingerprint:
2e49b70f3f7ec6…55c5affc5a Verified
Status:
On-Going
Physical progress:
100%
Timeline:
Start May 23, 2024 (2 yrs 5 mo ago)
Description:
ROAD WIDENING - PRIMARY ROADS - MANILA EAST RD (ROSARIOCAINTA RD) - K0016 + 434.22 - K0017+131
Category:
GAA 2024 OO-1
Implementing office:
DPWH Metro Manila 1st DEO · National Capital Region
Contractor:
4 J'S CONSTRUCTION SERVICES · DPWH contractor code 56647
Contract amount:
₱19,239,643.74 (₱19.2M)
Funding source:
Regular Infra - GAA 2024 OO-1
Budget year:
2024

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25DN0108May 29, 2025REHABILITATION OF DRAINAGE ALONG PAROLA STREET, BARANGAY SAN ANDRES CAINTA, RIZAL (FIRST DISTRICT)On-Going₱9.9M
25DN0074May 27, 2025REHABILITATION OF ROAD, BARANGAY MAMBUGAN AND BARANGAY MUNTINDILAW, ANTIPOLO CITY, RIZAL (FIRST DISTRICT)On-Going₱14.4M
25DN0078May 27, 2025REHABILITATION OF ROAD, PHASE 2, BARANGAY MAYAMOT, ANTIPOLO CITY, RIZAL (FIRST DISTRICT)On-Going₱9.6M
25DN0015May 23, 2025ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - CAINTA - KAYTICKLING - ANTIPOLO - TERESA - MORONG RD - K0020+402 - K0020+594, K0020+800 - K0019+222, RIZAL (FIRST DISTRICT)Completed₱14.1M
25DN0023May 23, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE, HALANG CREEK, PHASE 4, BARANGAY MAYAMOT, ANTIPOLO CITY, RIZAL (FIRST DISTRICT)On-Going₱69.6M
25OB0450May 22, 2025REHABILITATION OF FLOOD MITIGATION STRUCTURE ALONG ILUGIN CREEK, PASIG CITY (PHASE 1)Completed₱47.3M
25D00064May 21, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BALANTI CREEK, CAINTA, RIZALOn-Going₱95.0M
25D00084May 21, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE, CAINTA RIVER, BARANGAY SAN JUAN, CAINTA, RIZALOn-Going₱94.1M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.