Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 24OB0488

DPWH infrastructure contract
Contract ID:
24OB0488
Fingerprint:
277d62123fd701…42d3487e15 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 10, 2024 (2 yrs 1 mo ago) · Target/actual end Feb 24, 2025
Description:
CONSTRUCTION (COMPLETION) OF NACIDA INCUBATOR FACILITY INCLUDING SITE DEVELOPMENT, BARANGAY CONCEPCION DOS, MARIKINA CITY
Category:
Buildings and Facilities
Implementing office:
DPWH Metro Manila 1st DEO · National Capital Region
Contractor:
Contract amount:
₱73,120,510.13 (₱73.1M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25DN0104Jun 16, 2025ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - CORAZON C. AQUINO AVE. - K0029+580 - K0030+197 ANTIPOLO CITY (SECOND DISTRICT)On-Going₱18.7M
25DN0105Jun 16, 2025ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - MARIKINA - INFANTA RD - K0035+908.00 - K0036+000.00 ANTIPOLO CITY (SECOND DISTRICT)Completed₱4.8M
25DN0113Jun 16, 2025ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - MARIKINA - INFANTA RD - K0035+000.00 - K0035+738.00 ANTIPOLO CITY (SECOND DISTRICT)Completed₱30.9M
25DO0077Jun 5, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD BARANGAY SILANGAN TO BARANGAYOn-Going₱47.2M
25DN0096May 29, 2025ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - CORAZON C. AQUINO AVE. - K0029+400 - K0029+500, ANTIPOLO CITY (SECOND DISTRICT)Completed₱5.1M
25DN0100May 29, 2025IMPROVEMENT OF ROAD, OLALIA ROAD, PHASE II, BARANGAY STA CRUZ AND BARANGAY DELA PAZ, ANTIPOLO CITY (FIRST DISTRICT)On-Going₱9.6M
25DN0102May 29, 2025CONSTRUCTION OF SLOPE PROTECTION STRUCTURE, PUROK 5, ZONE 8, BARANGAY CUPANG, ANTIPOLO CITY, RIZAL (SECOND DISTRICT)On-Going₱5.0M
25DN0103May 29, 2025CONSTRUCTION OF SLOPE PROTECTION, BO. CUPANG/ LITTLE TONDO, BARANGAY CUPANG, ANTIPOLO CITY, RIZAL (SECOND DISTRICT)On-Going₱5.0M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.