Project 24PA0076

DPWH infrastructure contract
Contract ID:
24PA0076
Fingerprint:
df01b0059ed908…940b871a40 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 8, 2024 (2 yrs 7 mo ago) · Target/actual end Oct 31, 2024
Description:
CONSTRUCTION OF LANGIDEN BRIDGE, PHASE 4, SUYO & NALNAS-DALAYAP, LANGIDEN & PIDIGAN, ABRA
Category:
GAA 2024 SSP
Implementing office:
DPWH Abra DEO · Cordillera Administrative Region
Contract amount:
₱148,497,999.91 (₱148.5M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25PA0028Mar 26, 2025CONSTRUCTION OF SLOPE PROTECTION, ABRA RIVER IRRIGATION SYSTEM, TAYUM, BANGUED & PIDIGAN, ABRAOn-Going₱13.8M
25PA0033Mar 26, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY MALAPAAO, LANGIDEN, ABRAOn-Going₱4.7M
25PA0042Mar 13, 2025SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, REHABILITATION OF ROAD, SUYO-SAN DIEGO ROAD, PIDIGAN, ABRAOn-Going₱45.9M
24PA0156Jul 24, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY POBLACION WEST, PIDIGAN, ABRACompleted₱5.0M
24PA0080Mar 6, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY POBLACION EAST, PIDIGAN, ABRACompleted₱5.0M
24PA0074Feb 29, 2024SUSTAINABLE INFRASTRUCTURE PROJECT ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDING/ FACILITIES, CONSTRUCTION OF ROAD, LANGIDEN, ABRAOn-Going₱27.8M
24PA0029Feb 13, 2024OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVER, CONSTRUCTION OF QUILIAT FLOOD CONTROL ALONG ABRA RIVER, QUILIAT, LANGIDEN, ABRAOn-Going₱138.3M
23PA0221Oct 12, 2023SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, REHABILITATION OF MUSILING BAAC-QUILLAT POBLACION ROAD, LANGIDEN, ABRAOn-Going₱96.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.