Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 24PA0125

DPWH infrastructure contract
Contract ID:
24PA0125
Fingerprint:
0db5d259b46952…e09d5e38b7 Verified
Status:
On-Going
Physical progress:
87.8%
Timeline:
Start May 20, 2024 (2 yrs 5 mo ago)
Description:
CONCRETING OF SITIO SINABAAN, BRGY. TAGODTOD TO BRGY. LAGUIBEN FMR, BRGY. TAGODTOD AND BRGY. LAGUIBEN, LAGANGILANG, ABRA
Category:
Roads
Implementing office:
DPWH Abra DEO · Cordillera Administrative Region
Contractor:
739 BUILDERS · DPWH contractor code 31174
Contract amount:
₱9,452,181.77 (₱9.5M)
Funding source:
Outside Infra - GAA 2024 DA FMR
Budget year:
2024

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
59f4136ad46e…May 1, 2024DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ABRA ED₱9,452,181.77

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25PA0137Apr 8, 2025BASIC INFRASTRUCTURE PROGRAM (BIP)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, REHABILITATION OF ROAD, LAGANGILANG, ABRAOn-Going₱45.7M
25PA0032Mar 26, 2025CONSTRUCTION OF SABO DAM, LAGANGILANG IRRIGATION SYSTEM, LAGANGILANGOn-Going₱13.9M
25PA0007Feb 26, 2025ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM ASSET PRESERVATION PROGRAM PREVENTIVE MAINTENANCE-SECONDARY ROADS, ABRA-KALINGA RD-K0451+812-K0454+000, K0461+360-K0463+000, K0465+680-K0467+000, K0477+000-K0477+324On-Going₱50.9M
24PA0195Jan 14, 2025CONSTRUCTION OF AGUET FLOOD CONTROL STRUCTURE ALONG ABRA RIVER BASIN, BARANGAY AGUET, LAGANGILANG, ABRAOn-Going₱137.6M
24P00058Sep 30, 2024UPGRADING OF COLLEGE LIBRARY, LAGANGILANG CAMPUS - ABRA STATE INSTITUTE OF SCIENCES AND TECHNOLOGY, LAGANGILANG, ABRAOn-Going₱29.8M
24PA0092Mar 18, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, LAGANGILANG, ABRAOn-Going₱4.9M
24PA0003Feb 19, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY NAMIT-INGAN, DOLORES, ABRAOn-Going₱4.7M
24PA0011Feb 19, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY TAGODTOD, LAGANGILANG, ABRACompleted₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.